390 likes | 504 Vues
OVER-THE-RHINE. PLAYGROUND SCHEDULED TO BE COMPLETE OCTOBER 2011. WASHINGTON PARK SPRING EVENT PROGRAMMING. 3CDC Spring Events: Sunday, March 17: St. Patrick’s Day Celebration Monday, April 1: Reds’ Opening Day Celebration April 5 – April 26: EcoSculpt Art Installation
E N D
WASHINGTON PARK SPRING EVENT PROGRAMMING • 3CDC Spring Events: • Sunday, March 17: St. Patrick’s Day Celebration • Monday, April 1: Reds’ Opening Day Celebration • April 5 – April 26: EcoSculpt Art Installation • Monday, April 22: EcoSculpt Awards Ceremony • Fridays, May 3 – May 24: SCPA in the Park • Friday & Saturday, May 3 - May 4: Spring Beer Tasting • Friday, May 10: Clambake With The King
WASHINGTON PARK EVENT PROGRAMMING • 3CDC Weekly Events: • Sundays 6‐9 p.m. (Civic Lawn): Performing Arts, June 2 – September 8 • Mondays 7‐9 p.m. (Bandstand): Farmers Market, June 3 – August 26 • Tuesdays 7‐9 p.m. (Bandstand): Dance Under the Stars, May 28 – September 3 • Wednesdays 6‐9 p.m. (Bandstand): CSL Kickball League, May 29 – September 4 • Wednesdays 7‐9 p.m. (Bandstand): Jazz in the Park, May 29 – September 4 • Thursdays 7‐9 p.m. (Bandstand): Bandstand Bluegrass, May 30 – September 5 • Fridays 7‐10 p.m. (Civic Lawn): Friday Flow (R&B/Soul), May 31 – September 6 • Saturdays 9‐11 a.m. (Civic Lawn): Yoga in the Park, June 1 – September 7 • Saturdays 12‐2 p.m. (Bandstand): Curiosity Saturday, June 1 – August 24 • Saturdays 9‐11 p.m. (Civic Lawn): “Date Night” movies, June 1 – September 7
RESIDENTIAL SALES Gateway I,II,III & IV: 185 of the 186 condos (99%) are sold
RESIDENTIAL LEASING Gateway I,II,III & IV: 68 of the 68 apartments (100%) are leased
COMMERCIAL LEASING 80% of 103,000 SF commercial space leased. The Lackman Bakersfield 1215 Coffee Lab & Wine Bar Senate A Tavola Sloane Boutique
COMMERCIAL LEASING 80% of 103,000 SF commercial space leased. The Anchor Kaze Quán Hapa Quán Hapa The Anchor Kaze
COMMERCIAL LEASING KAZE, 1400 VINE STREET
COMMERCIAL LEASING HAPA,1331 VINE STREET
COMMERCIAL LEASING • Coming Soon: • Zula, 1400 Race Street • Currently negotiating multiple letters of intent; would bring total leased SF to 80% (82,000 out of 103,000 SF) of available space.
3CDC OTR DEVELOPMENT Future/ Land Bank Complete/ Under Construction Mercer Commons/ Gateway V
MERCER COMMONS • Phase I • 3,900 SF Commercial/Office • 28 Condos • 340-space Parking Garage • CDF committed $2.56 million of state and federal NMTC • Phase II • 67 Apartments (30 affordable) • 10,600 SF commercial space • OHFA awarded project low income housing tax credits and also received historic tax credits from State of Ohio • Phase III • 59 Apartments • 3,100 SF commercial space
BAKERY LOFTS 1421-1423 RACE • Developer: Urbanis LLC (Schickel Design) • Project Cost: $2.45 million • Project Size: 10,402 Gross SF • Project Summary: • 9 for-sale units • Estimated Completion Date: • March 2013
WESTFALEN LOFTS II 1426-1438 RACE • Developer: • 1438 Race LLC (Northpointe Group and John Hueber Homes - residential) • 3CDC - commercial • Project Cost: $8.6 million • Project Size: 32,798 Gross SF • Project Summary: • 33 for-sale units • 4,000 SF of commercial space • Estimated Completion Date: • September 2013
HUMMEL BUILDING 1401 ELM • Developer: Grandin Properties • Project Cost: $1.7 million • Project Size: 7,290 Gross SF • Project Summary: • 4 for-sale units • 1,880 SF commercial space • Estimated Completion Date: • May 2013
NICOLAY 1410 REPUBLIC • Developer: • Northpointe Group – residential • 3CDC - commercial • Project Cost: $2.34 million • Project Size: 13,293 Gross SF • Project Summary: • 10 for-sale units • 1,035 SF of commercial space • Estimated Completion Date: • June 2013
REPUBLIC STREET LOFTS 1406 & 1412 REPUBLIC • Developer: Northpointe Group • Project Cost: $1.99 million • Project Size: 8,230 Gross SF • Project Summary: • 9 for-sale units • Estimated Completion Date: • June 2013
B-SIDE APARTMENTS 1437 REPUBLIC & 13 W 15th • Developer: Mottainai Developers, LLC and 3CDC • Project cost: $4.5 million • Project Size: 22,000 gross SF • Project Summary: • 14 rental units • Estimated Completion Date: • July 2013
TEA COMPANY TOWNHOMES 18-20 W 13th & 1307 REPUBLIC • Developer: • City Lofts- residential • 3CDC - commercial • Project cost: $2.99 million • Project Size: 12,600 Gross SF • Project Summary: • 9 for sale units • 1,065 SF of commercial space • Estimated Completion Date: • December 2013
3CDC OTR DEVELOPMENT Land Banked/ Future Projects Complete/ Under Construction Mercer Commons/ OTR Phase V
3CDC OTR DEVELOPMENT Land Banked/ Future Projects Complete/ Under Construction