An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Recap from last time -I • Given a system of periodic tasks:  = {1, 2,... n}; i = (Ti, Ci) • Schedule using static priorities (of the first kind) • Two approaches: • partitioning • Dhall (1977), Dhall & Liu (1979): min #-procs for given  • Baker & Oh (1998): utilization bound for fixed m • non-partitioning • (John generalizes...) • In both approaches, feasibility-determination is NP-H in the SS (Leung & Whitehead -- from bin-packing) • The two approaches are incomparable

  2. Recap from last time - II • RM may have arbitrarily low utilization (the “Dhall effect”) • An upper bound on the achievable utilization of any static-priority scheme... Question:Is this bound tight? (Prove for m=2!) I.e., Given with [ (SUM j :  j : Ci /Ti)  4/3], prove that there is a static priority-assignment for which results in all deadlines being met.

  3. A detour: Not-quite-static priorities Question:Construct a similar upper bound for priority-assignment schemes of type “2”. (Is this tight? For n=2?) I.e., Given with [ (SUM j :  j : Ci /Ti)  3/2], prove that there is a static priority-assignment for which results in all deadlines being met.

  4. This paper -I • Obs 1 & 2: increasing period may reduce feasibility • (reason: parallelism of processor left over by higher-pri tasks increases) • Obs 3: Critical instant not easily identified • Obs 4: Response time of a task depends upon relative priorities of higher-priority tasks • ==> the Audsley technique of priority assignment cannot be used • Theorem 1: A sufficient condition for feasibility • idea of the proof • possible problems?

  5. Recap • Phil’s example of EDF anomaly • John’s generalization of partitioning/ non-partitioning • Shelby -- all about bin-packing Priorities task-level static job-level static dynamic Migration task-level fixed job-level fixed migratory bin-packing + LL (no advantage) bin-packing + EDF Baker/ Oh (RTS98) Jim wants to know... This paper Pfair scheduling

  6. This paper -I • Obs 1 & 2: increasing period may reduce feasibility • (reason: parallelism of processor left over by higher-pri tasks increases) • Obs 3: Critical instant not easily identified • Obs 4: Response time of a task depends upon relative priorities of higher-priority tasks • ==> the Audsley technique of priority assignment cannot be used • Theorem 1: A sufficient condition for feasibility • idea of the proof • possible problems?

  7. This paper -II “Circumventing Dhall’s effect” [Dhall’s effect: 1 = 2 = ... = m = (2, 2); m+1 = (1+ , 1) ] • Would like m+1 to have higher priority: Least slack assignment of priorities? • doesn’t quite work • TkC priority assignment: • choose a constant k • for each i = (Ti, Ci), priority-number of i := Ti - k  Ci • lowest priority-number gets highest priority • Seems a reasonable idea, but...

  8. This paper -III Deep thoughts about TkC: (priority-number of i := Ti - k  Ci) k=0: RM • not good: Dhall’s effect • k very large: assign priorities according to Ci’s • not good: 1=2= (100,1); 3=4= (10000,100) is infeasible on 2 procs • k somewhere in between...

  9. This paper -IV Why I don’t like TkC • Where’s the simple idea? • Conjecture is that (m+1) tasks is the worst-case... • goes against uniprocessor experience To disprove: (as opposed to not believe) • find a counterexample to the utilization bound • (likely easiest for m=2 -- static least-slack)

  10. How would we approach this problem? • Special cases (e.g., harmonic task sets) • Different kinds of priority schemes • priority-number of i = f(i) • relative priorities of two tasks depends upon only the two tasks • must examine all tasks prior to assigning priorities • Implications to on-line admission control

  11. Tractable special cases? Harmonic task sets • Result: Critical instant is easily identified • Result: Priority detemination remains NP-H in the SS • (since the Leung/Whitehead proof had all periods equal) Question:What about fixed number of processors? • (provably NP-H, but in the ordinary sense, for m=2)

  12. Open problems • Is the upper bound on achievable utilization tight? • Is the type-2 priority bound tight? • Any results on harmonic task sets? • [Uniprocessors:] Think deep thoughts about type 2 vs type 3 priority-assignment