1 / 26

Initial Operation & Requirements on the Machine

Initial Operation & Requirements on the Machine. R. Bailey AB LHC Operations. Global requirements on the machine. Highest energy proton collisions for ATLAS and CMS Nominal luminosity 10 34 cm -2 s -1 in points 1 and 5 Highest energy proton collisions for LHCb

orla-spence
Télécharger la présentation

Initial Operation & Requirements on the Machine

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Initial Operation&Requirements on the Machine R. Bailey AB LHC Operations R.Bailey, LHCMAC, June 2005

  2. Global requirements on the machine • Highest energy proton collisions for ATLAS and CMS • Nominal luminosity 1034 cm-2 s-1 in points 1 and 5 • Highest energy proton collisions for LHCb • Nominal luminosity ~ 5 1032 cm-2 s-1 in point 8 • Proton collisions @ various energies for ALICE • Nominal luminosity ~ 1030 cm-2 s-1 in point 2 • Ion collisions @ various energies for ALICE • Nominal luminosity ~ 1027 cm-2 s-1 in point 2 • ATLAS and CMS will also take data • Proton collisions @ various energies for TOTEM Proton luminosity running Dedicated Dedicated R,Bailey, LHCMAC, June 2005

  3. Lower energy runs - From Chamonix XIV - • TOTEM would like to have low energy runs during the first phase of the LHC operation: • √s= 1.8 TeV for direct comparison with TEVATRON • √s ~ 8 TeV to measure • ALICE would like to have a dedicated pp run at √s= 5.5 TeV (nucleon-nucleon √s for nominal Pb-Pb runs) for a direct comparison of the Pb-Pb and pp data. A lower energy Pb-Pb run may be requested too. However both requests are for a later stage of the LHC operation • Lower energy pp runs during early running are also discussed • Low energy runs are currently neither in the ATLAS nor in the CMS baseline physics program. However this request may come at a much later phase of the LHC operation R,Bailey, LHCMAC, June 2005

  4. Proton luminosity running - From Chamonix XIV - HSM -> 4 l (MHiggs = 140-155 GeV and 190-450 GeV) can be discovered with ~ 4 fb-1 Some supersymmetry can be discovered at more modest luminosities ~ 1 fb-1 Potential for b-physics right from startup ATLAS and CMS • Minimize event pileup early on • Go to 25ns as soon as possible • Will make use of any beam for detector commissioning LHCb • Tune IP8 to optimize luminosity (1m <  *>50m) • Go to 25ns as soon as possible (optimized for ~ 1 events/crossing) • Dipole polarity change ~ every fill ALICE • Will use proton beams (intrinsic interest and reference data) • Tune IP2 to optimize luminosity (0.5m <  *>50m) • Magnet polarities change ( + - 0 ) a few times per year (106 seconds @ <L> of 1033 cm-2 s-1 = 1 fb-1) R,Bailey, LHCMAC, June 2005

  5. High luminosity running • Eventual goal: luminosity of 1034 cm-2 s-1 (ATLAS & CMS) R,Bailey, LHCMAC, June 2005

  6. 2808 is a lot of bunches per beam • Filling scheme requires 12 SPS cycles per beam • Each with 2,3 or 4 batches of 72 bunches • Crossing angle needed • Emittance conservation with 1011 protons per bunch through • Injecting • Ramping • Squeezing to 0.55m • This is going to take us a little while !!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!! R,Bailey, LHCMAC, June 2005

  7. 362MJ is a lot of beam energy to handle R,Bailey, LHCMAC, June 2005

  8. So how to get there ? • Both machine and experiments will have to learn how to stand running at nominal intensities • An early aim is to find a balance between robust operation and satisfying the experiments • Maximize integrated luminosity • Minimize event pile-up (to event + 2) • Avoid quenches (and damage) • Higher * to avoid problems in the (later part of) the squeeze • Reduce total current to reduce stored beam energy • Lower ib • Fewer bunches • Reduce energy to get more margin ? • Against transient beam losses • Against magnet operating close to training limit • Hardware commissioning will tell us more R,Bailey, LHCMAC, June 2005

  9. Other considerations • Electron cloud ( LHC simulations and SPS experience ) • ib < 35% nominal for 25ns spacing • ib ~ nominal for > 50ns • With lower currents in mind, two machine systems will be staged • Only 8 of 20 beam dump dilution kickers initially installed • Total beam intensity < 50% nominal • Install the rest when needed • Collimators ( robustness, impedance and other issues ) • Phased approach • Run at the impedance limit during phase I • Lower currents • Higher * Under review! R,Bailey, LHCMAC, June 2005

  10. Proposal for early proton running Phase I collimators and partial beam dump • Pilot physics run with few bunches • No parasitic bunch crossings • Machine de-bugging no crossing angle • 43 bunches, unsqueezed, low intensity • Push performance (156 bunches, partial squeeze in 1 and 5, push intensity) • 75ns operation • Establish multi-bunch operation • Relaxed machine parameters (squeeze and crossing angle) • Push squeeze and crossing angle • 25ns operation with Phase I collimators + partial beam dump • Needs scrubbing for higher intensities ( ib > 3 - 4 1010 ) Phase II collimators and full beam dump 4. 25ns operation • Push towards nominal performance R,Bailey, LHCMAC, June 2005

  11. Commissioning for Stage 1 - From Chamonix XIV - - 450GeV machine - R,Bailey, LHCMAC, June 2005

  12. - From Chamonix XIV - Commissioning for Stage 1 - Ramp and Squeeze - R,Bailey, LHCMAC, June 2005

  13. - From Chamonix XIV - - Ramp and Squeeze - - 450GeV machine - R,Bailey, LHCMAC, June 2005

  14. - From Chamonix XIV - Along the way • Equipment commissioning with beam • Machine protection commissioning • Instrumentation commissioning • First turn i.e. immediately • Screens, BPMs, fast BCT, BLMs • Circulating beams at 450 GeV • BPMs, DC BCT & lifetime, BLMs • Transverse diagnostics • Emittance: wire scanners.. • Snapback and Ramp • Chromaticity, PLL • Orbit • BLMs to BIC etc. • Checks with beam • BPM Polarity, corrector polarity, BPM response • Beam measurements • beam parameter adjustment, energy, linear optics checks, aperture • etc. etc. R,Bailey, LHCMAC, June 2005

  15. Stage 1 – pilot run luminosities • No squeeze to start • 43 bunches per beam (some displaced in one beam for LHCb) • Around 1010 per bunch • Push one or all of • Partial optics squeeze in 1 and 5 (2m ???) • Increase bunch intensity • 156 bunches per beam (some displaced in one beam for LHCb) R,Bailey, LHCMAC, June 2005

  16. Stage 2 – 75ns luminosities • Partial squeeze and smaller crossing angle to start • Luminosity tuning, limited by event pileup • Establish routine operation in this mode • Move towards nominal squeeze (1m ???) and crossing angle • Increase bunch intensity ? • Tune IP2 and IP8 to meet experimental needs • Down in IP8 (1m ???) • Up in IP2 (50m ??? Then transverse beam displacement probably needed) R,Bailey, LHCMAC, June 2005

  17. Stage 3 & 4 – 25ns luminosities • Production physics running • Start with bunch intensities below electron cloud threshold • Scrubbing run (1-2 weeks) • Increase bunch intensities to beam dump & collimator limit • Install beam dump kickers • Install phase II collimators • Increase bunch intensities towards nominal • Tune IP2 and IP8 to meet experimental needs • Transverse beam displacement certainly needed in IP2 Long shutdown (6months) R,Bailey, LHCMAC, June 2005

  18. * adjustments - Squeeze • Squeeze • Going to be tricky to set up in any case (Optics changes and collimators) • Foresee to do it after ramp to physics energy • IP 1 and 5 to 2m or maybe 1m should become routine • IP 8 to values between 10m and 1m more tricky • IP 2 to values between 10m and 50m more tricky • Squeezing at other energies will be even more tricky • Stick with injection optics at lower energies ? R,Bailey, LHCMAC, June 2005

  19. Filling • Filling • All the beams below have been made, but … • Complicated scheme for all physics runs • 12 SPS cycles per LHC ring • Procedures defined (LHC is the master) • Need to demonstrate that we can do it • Reliability implications for injectors • Compounded by LHCb magnet polarity switch R,Bailey, LHCMAC, June 2005

  20. Ions Experiment side • ALICE, ATLAS and CMS will all take Pb-Pb data • Detectors and machine will be already commissioned with pp • ALICE requests • 4 week ion runs at the end of each year • first short run as early as possible Machine side • Start with early ion scheme (62 bunches instead of 592, 7 107 ions per bunch) • Will have to • Re-commission injection, first turn • Set up RF capture and instrumentation • Re-commission ramp and squeeze • Establish collisions • Could do (some of) this early on if injectors are ready (same optics as for p) • Ion runs could provide cool down of PS SPS LHC after proton operation • After early ion scheme run, increase number of bunches • Move to nominal when possible - From Chamonix XIV - Estimate 1-3 weeks for first setup Followed by physics run R,Bailey, LHCMAC, June 2005

  21. Ion filling and luminosities R,Bailey, LHCMAC, June 2005

  22. TOTEM A standard TOTEM year would be • σtot measurement high priority • Nominal emittance OK for σtot, 1 μm needed for elastic scattering • 3 * 1 day runs at * of 1540m with 43 or 156 bunches per beam • 2 * 1 day runs at * of 18m with 2808 bunches per beam (25ns) ATLAS requests a period of a few weeks after first years of running Machine side • Special machine conditions, similar to polarisation runs at LEP • Very demanding on beam and optics quality, and for collimation • Initial setup will take several days (maybe better dispersed) • Subsequent setups should take a shift or two • Longer runs may be more efficient if machine reproducibility is an issue - From Chamonix XIV - R,Bailey, LHCMAC, June 2005

  23. TOTEM luminosities • Total Cross Section and Elastic scattering • Diffraction and minimum bias • Characterized by • Several 1 day runs per year (starting early) • Some single beam runs • 43 and 156 bunches per beam (as during Stage 1) • IP5 * = 1540m • IP5 * = 18m R,Bailey, LHCMAC, June 2005

  24. Scheduling - From Chamonix XIV - Every year we will need a long shutdown (3-4 months) At the end of every shutdown • Close the machine personnel access system • Get all equipment ready for beam (machine checkout, ~ 4 weeks) • Get machine ready for operation (setup with beam, 2-3 weeks) During periods of operation • Need regular technical stops (3 days every month) • Interventions need careful but flexible planning • Get machine ready for operation (1 day) • Machine development (around 15% during first years) • Operations for physics • Access as required for unscheduled stops R,Bailey, LHCMAC, June 2005

  25. Breakdown of a normal year - From Chamonix XIV - 7 • 140 days for physics per year • Not forgetting ion and TOTEM operation • Leaves ~ 100 days for proton luminosity running • ? Efficiency for physics 40% ? • 40 days ~ 1000 h ~ 4 106 s of colliding beams / year R,Bailey, LHCMAC, June 2005

  26. So the first few years could look like … • Starting in 07, phase II collimators in 09/10 R,Bailey, LHCMAC, June 2005

More Related