This update outlines the progress of solar installations at various Madison Elementary schools, including Rose Lane and Park Elementary. Key milestones include substantial completion expected by September 23, 2013, and the first day of solar generation on September 26, 2013. Other ongoing projects include cafeteria remodels at Madison Heights and Madison Meadows, and structural improvements such as sidewalk replacement and roof work. The next step involves site evaluations and preliminary designs for further solar enhancements and applications for rebates.
E N D
Madison Elementary School District Mr. Calvin Bond Project Update August 2013
Solar - Schedule of Completion • Structural and panel set- 8/22/13 • Broken sidewalk replacement- 8/26/13 • Installation of turf and DG- 9/16/13 • Substantial completion- 9/23/13 • First day of generation- 9/26/13 • Final Completion- 10/14/13
The Next Step in Solar • Site evaluations later this week • Preliminary design by 8/29 • Submitting applications to APS for rebates by 8/30
Upcoming Projects • Madison Heights kitchen remodel • Madison Meadows front office remodel • Non-skid surfacing on exterior stairs • Roof replacement at Heights • Daylighting in dining areas at • Heights, Park and Rose Lane Questions: