BG # 1 Example-I of Project Planning Project Plan Example Project Management Process Area
Software Quality Engineering Example-I of Project Plan
BG # 1 Example-I of Project Planning Project Plan Example Project Management Process Area
Software Quality Engineering Example-II of Project Plan
BG # 1 Example-II of Project Planning Project Plan Example Project Management Process Area
BG # 1 Example-II of Project Planning Baseline Project always help to manage Change Requests. Project Management Process Area
Software Quality Engineering Example-III of Project Plan
BG # 1 Example-II of Project Planning Project Plan Example Project Management Process Area
BG # 1 Example-II of Project Planning Baseline Data is always not what actual data will reflect Project Management Process Area
Software Quality Engineering Project Tracking and Control
BG # 1 Project Tracking and Control Tracking and Controlling ensure project progress as per plan. Daily Scrums are to ensure daily Progress Project Plan is key input for monitoring Project Management Process Area
BG # 1 Project Tracking and Control Weekly Status Meetings ensure overall progress of Project Weekly Status Reports by Key Artifacts. Project Management Process Area
Software Quality Engineering Example of Project Tracking and Control
BG # 1 Example of Project Tracking and Control Weekly Status Report Project Management Process Area
BG # 1 Example of Project Tracking and Control Depending on Nature of Project Multiple Status Reports can be generated Project Management Process Area
Software Quality Engineering Audit of Each Phase of PM Process Area
BG # 1 Audit of Each Phase of PM Process Area Audit of PM Process Area is as per PM Framework Project Manager is responsible to provide relevant data for Audit. Project Heath is determined by Audit Project Management Process Area
BG # 1 Audit of Each Phase of PM Process Area Audit Data Project Management Process Area
BG # 1 Audit of Each Phase of PM Process Area Audit Data is use to take corrective measures Project Management Process Area
Software Quality Engineering Earned Value Management
BG # 1 Earned Value Management (EVM) EVM is tool provide objective measure to project cost and schedule variance . It is Actual value completed successfully on a Project Project Management Process Area
BG # 1 Earned Value Management (EVM) Planned Value (PV) Actual Value (AV) Earned Value(EV) Project Management Process Area
BG # 1 Earned Value Management (EVM) To measure Planned effort vs effort spend it often misleading Project Management Process Area
Software Quality Engineering SPI and CPI
BG # 1 SPI and CPI Schedule Performance Index(SPI) is to determined project schedule SPI: Earned Valued (EV) / Planned Value(PV) Project Management Process Area
BG # 1 SPI and CPI SPI < 1.0 indicate Project is behind schedule Earned Value is less than Planned Project Management Process Area
BG # 1 SPI and CPI Cost Performance Index(SPI) is to determined project budget status CPI: Earned Valued (EV) / Actual Value(AV) Project Management Process Area
BG # 1 SPI and CPI CPI < 1.0 indicate Project is over budget Earned value is less than Actual Value Project Management Process Area
Software Quality Engineering Example-I of CPI and SPI
BG # 1 Example-I of CPI and SPI Example-I Project Management Process Area
BG # 1 Example-I of CPI and SPI Project is Over budget and behind schedule Project Management Process Area
Software Quality Engineering Example-II of CPI and SPI
BG # 1 Example-II of CPI and SPI Example-II Project Management Process Area
BG # 1 Example-II of CPI and SPI Project is Over budget and behind schedule Project Management Process Area
Software Quality Engineering Cavendish Software Chaos Report
Software Requirement Engineering vs Software Quality Engineering
Software Requirement Engineering vs Software Quality Engineering Cavendish Software Chaos Report Over a decade there is improvement project success. Main Challenge is to do Proper requirement Engineering
Software Quality Engineering Motivation for Software Requirements
Software Requirement Engineering vs Software Quality Engineering
Software Requirement Engineering vs Software Quality Engineering Motivation for Software Requirements Requirement Engineering is easier said than done Client usually underestimate writing requirements
Software Quality Engineering Why to Focus on Requirements
Software Requirement Engineering vs Software Quality Engineering Why to Focus on Requirements Missing Requirements Customer not involved Critical requirement missed
Software Requirement Engineering vs Software Quality Engineering Why to Focus on Requirements Wrong Requirements Mixing what and how Change Request Change is only Constant Out of Scope Requirements
Software Quality Engineering Effort-wise Distribution of SDLC
Software Requirement Engineering vs Software Quality Engineering
Software Requirement Engineering vs Software Quality Engineering Effort-wise Distribution of SDLC Ideally there should be 20% budget for Requirement Gathering Realistically it is considered as overhead
Software Quality Engineering Requirement Defined
Software Requirement Engineering vs Software Quality Engineering Requirements Defined Requirement Engineering is not a technical activity It is purely communicational activity Different stakeholders have different viewpoint