An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ECAL Monitoring System Ivan Korolko (ITEP Moscow) PRR, September 2004

  2. Outline Finalized light splitter Fiber bundles configuration Light distribution boxes LED drivers and PIN diode boards Planning

  3. Light splitters Produced and tested this summer 1) Very simple construction 2) Good uniformity of light yield for all fibers 3) Good reproducibility 4) High light yield

  4. Light splitters uniformity ● central fiber ● 1st circle ● 2nd circle ● 1.2 mm fibers

  5. Light splitters – LED housing

  6. Fiber bundles Corresponding number of fibers is grouped in bundle and molded with epoxy resin. Fibers in bundle have different length to lighten the connection to optical contacts. (max ~50cm) High temperature bending of fibers – technology optimization • requires quite some man power (now) • dangerous to break a fiber • HERA-B experience (curved fibers forming bundle)

  7. Fiber bundles configuration (1) Outer and Middle sections: Splitters 1 → 16+3 Inner section: Splitters 1 → 9+3

  8. Fiber bundles configuration (2) Inner section: reduced number of LEDs (factor 1.5)

  9. LEDs PiN diodes Trigger signals Outer 84 28 84 Middle 56 14 56 Inner 88 22 88 Components of monitoring system

  10. Routing of bundles (1) 25 mm trays for inner ECAL section

  11. Routing of bundles (2) 37 mm trays for middle ECAL section

  12. Routing of bundles (3) 45 mm trays for outer ECAL section

  13. Light distribution boxes (1)

  14. Light distribution boxes (2)

  15. LDBs for one half of ECAL

  16. PiN diode board PiN diode Splitter LED LED driver LED-PiN fiber Bundles Light distribution box (fragment)

  17. 1st lower box Box size 720x880x120 Led driver 15x100 mm2 PIN diode board 40x100 mm2 Power for LEDs +5V, +25V Power for PINs +/-6V, +25V Trigger signals LED amplitude control voltages

  18. LED drivers (1) Dedicated ECAL version of LED driver (produced in IHEP) Several LED drivers produced and tested during this summer beam tests

  19. LED drivers (2) DS0026 became obsolete (still available from distributors) PCB design and prototypes exist for: • pin-to-pin compatible EL7212, ICL7667 • EL7104 • SN75372 DC isolation of the triggering signals requires individual triggering for each LED driver.

  20. PIN diode boards (1) Dedicated ECAL version of PIN diode board (produced in IHEP) PIN diode boards produced and tested during this summer beam tests

  21. PIN diode boards (2) Charge gain ~300 ENC ~5000 electrons δ function response ~10 ns. Dynamic range 12 bits The same clipping line as for PMTs is used Amplifiers are based on LMH6624 or EL5133

  22. Planning (1) Many changes during last months ECAL installation should be finished on 31 of July The whole planning is quite tense

  23. Planning (2) Production of bundles starting on 04/10/2004 special “long” room with shelves is ready Cutting of bundles starting on 25/10/2004 need to prepare cutting tools Should be finished in March Installation of bundles : 15/04/2005 – 15/05/2005

  24. Planning (3) Detailed design of LDBs : 15/12/2004 meeting in Moscow or at CERN (Stas) Production of LDBs starting on 15/01/2005 Installation of LDBs starting on 15/05/2005 Final connection of all components 01/06/2005 – 01/07/2005

  25. Planning (4) Production of LED housings 01/11/2004 – 1/03/2005 should be delivered to CERN in March LED drivers and PIN diode boards purchase of components – ASAP mass production 01/01/2005 – 01/03/2005 should be delivered to CERN in March temporary readout system to check the work of LEDs and PMTs ??? Seems to be useful ???