This document presents an overview of the EUSO Balloon Project, including a detailed schedule from mid-2012 to March 2014. Key procurement milestones are highlighted, detailing the manufacturing timeline for lenses, mechanical structures, and electronic components. Updates on the delivery of subsystems and critical milestones are provided, such as the completion of the EC Unit and the communication systems. The document emphasizes the structured timeline ensuring successful execution of the project, culminating in the readiness to fly by March 6th.
E N D
EUSO-BALLOON DESIGN REVIEW, 18.12.2012, CNES TOULOUSE Schedule Guillaume Prévôt APC, Paris • Introduction • Procurement status • Main milestones
Introduction • The schedule(EUSO-SCH-INST-005-APC_V1.0)has been made frommid 2012 to March 2014 with: • 3 weeks of margins • 7 weeks of holydays / year. Schedule
Procurement status • - Lenses:willbemanufactuedfromDecember the 10th.The 3 lenseswillbefinishedJune, the 10th. • Deliveryat IRAP of the 3 lensesaftermeasurements in US: July, the 27th • - Mechanical structure: will be received by IRAP June, the 10th. • - EEE: every electronics components are supplied or foreseen to be. No long-span delivery identified. • PDM: • -EC_ASIC board: EC_ASIC board FM will be produced April, the 2ndby LAL. • -HVPS boards: HVPS boards FM will be delivered April, the 2nd at APC. • PDM board: PDM board FM will be delivered March, the 12ndat APC. • DP: • -All the subsystems will be produced and tested April, the 2nd. Schedule
Main milestones Main milestones: - CRE AIT EC Unit May, the 29th - CRE AIT PDM July, the 3rd - CRE AIT DP June, the 25th - CRE AIT PDM + DP communication September, the 13rd - CRE AIT Instrument (after a rehaearsal of a campaign), ready to fly November, the 19th - Delivery at Timins, Canada (after 30 days shipment) February, the 18th - Ready to fly March, the 6th Schedule