1 / 13

BOX PUSHING TECHNOLOGY

BOX PUSHING TECHNOLOGY. By - Akshit Rajan. Conventional method. Open cut system Excavation Placing Covering Demerits Increased time for execution Interruption in traffic Cost factor was high. NEED FOR THE ALTERNATIVE.

rob
Télécharger la présentation

BOX PUSHING TECHNOLOGY

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BOX PUSHING TECHNOLOGY By - AkshitRajan

  2. Conventional method • Open cut system • Excavation • Placing • Covering • Demerits • Increased time for execution • Interruption in traffic • Cost factor was high

  3. NEED FOR THE ALTERNATIVE • Present day Intensity of Traffic, both Rail & Road due to the fast development, is very heavy it cannot the disturbed, for construction of under bridges or Canal Crossings, drainage etc by conventional i.e. open cut system. • Box Pushing Technique is developed where in R.C.C. Boxes in segments are cast out side and pushed through the heavy embankments of Rail or Road by Jacking.

  4. METHODOLOGY • Excavation • Casting of Thrust Bed • Fabrication of Front and Rear shield • Box Casting and placing • Pushing-shifting-pushing operation • Miscellaneous works • Precautions

  5. Excavation and casting of Thrust Bed • Open excavation is carried out for construction of Thrust bed

  6. Fabrication of Front Shield • Front Shield It is fabricated for cutting action and to provide support , to prevent caving in of soil.

  7. Fabrication of Rear Shield • Rear Shield • It is provided by anchoring steel plates on the face of bottom slab of RCC box to suitably distribute the jacking load.

  8. Box Casting And Pushing • The RCC Box is cast in segments of convenient lengths of Total pushing length. • The Box section is designed as per IRS / IRC codes of practice for loading. Concrete grade normally kept as M-35.  

  9. Precautions • Cutting edge of front shield is fabricated with adequate thickness of steel plate and the front edges of the steel plate are sharpened to facilitate penetration into the soil. • To prevent caving of earth during excavation quantity of earth shall be removed to barest minimum duly following the slop of cutting edge. • Guide channels to be provided in the thrust bed to guide the segments to ensure straight alignment • The level of the boxes should be continuously checked. • The Speed limit should be set to 20 km/h At the site of construction • The work should be stopped when a train is passing over the work.

  10. Photo Gallery

  11. THANK YOU

More Related