roger
Uploaded by
16 SLIDES
437 VUES
170LIKES

Earned Value System

DESCRIPTION

Earned Value System. Pioneered by U.S. Department of Defence to track schedule and cost in large projects in 1960s. Widely used by private sector around the world. NCR, Levi Strauss, Disney etc. System depends on a well-developed plan and schedule.

1 / 16

Download Presentation
Télécharger la présentation

Earned Value System

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Earned Value System • Pioneered by U.S. Department of Defence to track schedule and cost in large projects in 1960s. • Widely used by private sector around the world. • NCR, Levi Strauss, Disney etc. • System depends on a well-developed plan and schedule. • System is based on an accounting system called “earned value”. OPSM 639, C. Akkan

  2. Earned Value System • Consider the following example: • R&D project planned to last 10 months and cost $200,000 per month. • After 5 months, top management assesses the status of the project • Actual cost for the 5 month period: $1.3 million • Would it be accurate to conclude that the project has $300,000 cost overrun? OPSM 639, C. Akkan

  3. Earned Value System • Earned value system is an integrated cost/schedule system. System overview: • Develop a project plan and schedule as discussed earlier in this course. • Develop a time-phased budget. The cumulative values of these budgets will the baseline and called budgeted cost of the work scheduled (BCWS). • Collect actual costs for the work performed at the work package level. These costs will be called actual cost of work performed (ACWP). OPSM 639, C. Akkan

  4. Earned Value System • Collect the budgeted values of work actually performed. These will be called budgeted cost of work performed (BCWP). • Compute schedule variance as • SV = BCWP - BCWS • Compute cost variance as • CV = BCWP - ACWP • Prepare hierarchical status reports for each level of management. OPSM 639, C. Akkan

  5. Earned Value System WBS Cost Variance Schedule Variance Element BCWS BCWP ACWP BCWP - ACWP BCWP - BCWS A 100 100 110 -10 0 B 56 50 48 2 6 C 28 20 30 -10 58 184 170 188 • BAC:Budgeted cost at completion • CPI (Cost Performance Index) = BCWP/ACWP • =170/188 = 0.904 • SPI (Schedule Performance Index) = BCWP/BCWS • =170/184 = 0.924 OPSM 639, C. Akkan

  6. Earned Value System Cumulative cost BAC $370 BCWS ACWP $184 BCWP (earned value) Time Scheduled end today OPSM 639, C. Akkan

  7. Earned Value System • The main reason for creating a baseline is to monitor and report progress. Hence it is absolutely necessary that costs are time-phased in the baseline exactly as managers expect them to be “earned”. • Three common rules • 0/100 percent rule: 100% of the budget is earned when the workpackage is complete. OPSM 639, C. Akkan

  8. Earned Value System • 50/50 percent rule: 50% of the value earned when the workpackage is started and 50% is earned when the workpackage is completed. • Percent complete rule: Establish frequent checkpoints over the duration of the work package and assign completion percentages in terms of dollars. • This is the method used most frequently. • During monitoring the measure percent complete, it is common practice to limit amount earned by 80% until the work package is 100% complete. OPSM 639, C. Akkan

  9. Earned Value System • After the current status of the project is determined, one would want to revise the project’s total cost. This is referred to as EAC (Estimated cost at completion). • EAC: is equal to actual cost to-date plus revised estimated cost of the remaining work). • EAC = ETC + ACWP • ETC: Estimated cost to complete • Typically ETC is determined by making use of the CPI. OPSM 639, C. Akkan

  10. Earned Value System ETC = (BAC - BCWP)/CPI = (370 - 170) / 0.904 = 221.24 EAC = ETC + ACWP = 221.24 + 188 = 409.24 • VAC (Variance at Completion) = EAC - BAC VAC = 409.24 - 370 = 39.24 • TCPI (To Complete Performance Index) = (BAC - BCWP) / (EAC - ACWP) • Performance index of the remaining work for a given EAC. OPSM 639, C. Akkan

  11. Earned Value System • Let’s say we want EAC = 370, then TCPI = (370 - 170) / (370 - 188) = 1.099 OPSM 639, C. Akkan

  12. Earned Value System - Example • Some simplifying examples • Each cost account has only one work package and each cost account is represented by a single activity. • Project network early start times will serve as the basis for assigning the baseline values. • Except when the 0/100 rule or 50/50 rule is used, baseline values will be assigned linearly, unless stated differently. • From the moment work on an activity begins, some actual costs will be incurred each period until the activity is completed. OPSM 639, C. Akkan

  13. Earned Value System - Example OPSM 639, C. Akkan

  14. Earned Value System - Example 3 8 A2, 3 5 10 6 10 3 6 10 12 0 3 A6, 3 A8, 3 A3, 3 A1, 3 6 10 10 12 3 6 0 3 3 7 7 10 A4, 3 A7, 3 3 7 7 10 3 5 A5, 3 5 7 OPSM 639, C. Akkan

  15. Earned Value System - Example Project baseline budget EV Rules:1) 100 percent of budget when completed2) 50/50 percent when started and finished3) observed percent complete OPSM 639, C. Akkan

  16. Earned Value System - Example Status report at the end of period 4 OPSM 639, C. Akkan

More Related
SlideServe
Audio
Live Player
Audio Wave
Play slide audio to activate visualizer