wing-summers
Uploaded by
2 SLIDES
300 VUES
50LIKES

Earned Value Terminology

DESCRIPTION

Data Element. Term. Acronym. Scheduled Work. Budgeted Cost for Work Scheduled. PV (BCWS). Earned Value. Budgeted Cost for Work Performed. EV (BCWP). Actuals. Actual Cost of Work Performed. AC (ACWP). Work Variance. Schedule Variance. SV=EV-PV. Cost Variance. Cost Variance.

1 / 2

Télécharger la présentation

Earned Value Terminology

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Data Element Term Acronym Scheduled Work Budgeted Cost for Work Scheduled PV (BCWS) Earned Value Budgeted Cost for Work Performed EV (BCWP) Actuals Actual Cost of Work Performed AC (ACWP) Work Variance Schedule Variance SV=EV-PV Cost Variance Cost Variance CV=EV-AC Cost Performance Cost Performance Index CPI=EV/AC Sched. Performance Schedule Performance Index SPI=EV/PV Authorized Work Budget At Completion BAC=S (PV) Completion Cost Estimate to Complete ETC Forecasted Cost Estimate At Completion EAC=AC+ETC Completion Variance Variance At Completion VAC=EAC-BAC Earned Value Terminology

  2. Earned Value Data Elements Time Now EAC ETC VAC CBB=Contract Budget Base MR BAC(PMB) Projected Program Delay PV AC EV Schedule Variance Cost Variance Schedule Slip

More Related