SlideServe
Menu
Préférences
© SlideServe · v2026

Status Update on Front End Electronics for HTR Control Systems (March 1, 2007)

rufin avatar
4 diapositives · 210 Views · Dec 26, 2013

In the March 1, 2007 DES Meeting, T. Shaw reported on the HTR control system developments. Key updates included the delivery of the 12-channel board to SiDET and initial testing revealing high noise levels (~30e-). The team is working on a test stand while addressing cabling issues within the dewar. Contracts for AlN boards were confirmed, with improvements planned for FFC connections. Additionally, preparations for cooling the Multi CCD Dewar are underway, with software and hardware deemed satisfactory. Future collaboration meetings are in planning for mid-July to assess progress.

Status Update on Front End Electronics for HTR Control Systems (March 1, 2007) - slide 1
01 / 4Status Update on Front End Electronics for HTR Control Systems (March 1, 2007)
1 / 17

Télécharger la présentation

Status Update on Front End Electronics for HTR Control Systems (March 1, 2007)
Une image / un lien ci-dessous est fourni (tel quel) pour télécharger la présentation

Politique de téléchargement : le contenu du site vous est fourni TEL QUEL pour votre information et votre usage personnel ; il ne peut être vendu, concédé sous licence ni partagé sur d’autres sites sans l’accord de son auteur.Le contenu vous est fourni TEL QUEL, pour votre information et votre usage personnel uniquement. Téléchargez la présentation en cliquant sur ce lien. Lors du téléchargement, si vous ne parvenez pas à télécharger une présentation, l’éditeur a peut-être supprimé le fichier de son serveur.Pendant le téléchargement, si vous ne parvenez pas à obtenir une présentation, le fichier a peut-être été supprimé par l’éditeur.

F I N

Plus de contenu associé

Transcription de la présentation
  1. Front End Electronics Status DES Meeting, March 1, 2007 T. Shaw

  2. FEE Status • HTR control system has been delivered to SiDET • 12 Channel Board • Initial tests allowed us to readout CCD • Juan shows that the noise is too high ~30e- • We are investigating this; we are in the process of re-assembling a working 12-Channel board teststand on WH14 with 2nd board set • AlN Boards • Contracts entered in system for two types of AlN Boards • Nanonics w/JFET • FFC w/JFET • Cabling issues • We are trying to solve cabling issues inside dewar • We are handling the dewar wiring a lot more with the pedestal packages • Have seen a variety of problem • Open connectors • Open contacts • improperly seated cables • Have identified better FFC connector vendor, will swap out some connectors • Need to slightly build up thickness of the flat flex cable DES Meeting, March 1, 2007 T. Shaw

  3. Status • Multi CCD Dewar • getting ready to cool down MCD; two CCD readout • Software, hardware look OK • need a few days to do noise studies with external cabling • From Madrid • The Clock Board is under test • Monsoon system (MCB and CBB) is up and running • From Barcelona • See Laia’s slides DES Meeting, March 1, 2007 T. Shaw

  4. Other News • We need to start thinking about the next FE Electronics collaboration meeting • Target date is mid-July • At that time we should be able to review the status of • power supply design • crate design • 12-channel board performance • Clock Board performance • S-link and the MCB • Crate Synchronization plans • ……. DES Meeting, March 1, 2007 T. Shaw