An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Lecture 28: Supply Chain Scheduling 2 © J. Christopher Beck 2005

  2. Outline • Discrete Manufacturing vs Continuous Manufacturing • What Difference Does It Make? • A Typical Framework for Supply Chain Optimization • Medium Term Planning • Short Term Scheduling • Information System Issues © J. Christopher Beck 2005

  3. Supply Chain Scheduling © J. Christopher Beck 2005

  4. Discrete vs. Continuous Manufacturing • Continuous (process) production • Main inventory/products are finely divisible • Steel, shampoo, paper • Discrete production • Main inventory/products are individually countable • Cars, computers, consumer electronics • Scheduling problems are different © J. Christopher Beck 2005

  5. Continuous:1. Main Processing • Raw materials aretransformed to intermediate products • Machines have high start-up/shutdown costs and • High changeover costs • Often fixed batch sizes • Usually run 24/7 © J. Christopher Beck 2005

  6. Continuous:2. Finishing • Products of mainprocesses are “specialized” • Cut, bent, extruded, painted, printed, … • Often these are commodities • Many clients • Mix of make-to-stock, make-to-order • Due dates, sequence dependent changeovers, and inventory management are important © J. Christopher Beck 2005

  7. Discrete:1. Primary Conversion • Like finishing in continuous • Stamping, bending, cutting • Process is generally pretty simple • Output is often a part • Car body part, computer case, … • Schedule is often integrated with downstream processes © J. Christopher Beck 2005

  8. Discrete:2. Main Production • Many differentoperations of many tools • 100 step process for semiconductors! • Machines are very expensive • Often organized like a job shop • Each order has its own route, quantity, due date • Sequence dependent changeovers © J. Christopher Beck 2005

  9. Discrete:3. Assembly • Put together parts • Machines are cheap but material handling is important • Assembly lines • cars or consumer electronics • Due dates, changeovers, sequencing, … © J. Christopher Beck 2005

  10. Table 8.1 © J. Christopher Beck 2005

  11. Table 8.2 © J. Christopher Beck 2005

  12. Supply Chain Decomposition © J. Christopher Beck 2005

  13. Medium-term Aggregation • Time abstraction • 1 unit = 1 day or 1 week • Product abstraction • Work at product “family” level • e.g., Tuborg beer, not 6-pack, 12, 24, keg, … • Cost/job/capacity abstraction • Average processing times • Sequence dependencies ignored • Factory treated as a single resource © J. Christopher Beck 2005

  14. Medium-term Planning Results • Daily or weekly • Demand for product families at each facility • Inventory levels • Transportation requirements • No detailed scheduling has been done! © J. Christopher Beck 2005

  15. Medium-term Constrains Short-term © J. Christopher Beck 2005

  16. Medium-term Decouples Short-term © J. Christopher Beck 2005

  17. Short-term Scheduling Uses More Precise Data • Time in minutes or seconds • Horizon ≈ week, 2 weeks • Jobs and resources are detailed • Set-up time/cost are taken into account • Products not just product families • Demand for each product is represented © J. Christopher Beck 2005

  18. Problem • Short term schedule solution may not exist! • Why? • May require feedback of information to the medium-term and a resolve • Carlsberg takes 10-12 hours for a medium-term solve … © J. Christopher Beck 2005

  19. Feedback Mechanism Needed © J. Christopher Beck 2005

  20. Information Infrastructure Requirements © J. Christopher Beck 2005