1 / 12

Preliminary Cost Effectiveness Analysis and WFD economics update

Preliminary Cost Effectiveness Analysis and WFD economics update. Kevin Andrews. pCEA - Aim. To minimise the amount of new cost-effectiveness analysis that is needed by drawing on existing information, expertise and processes, To maximise the amount of analysis done at the national level.

saman
Télécharger la présentation

Preliminary Cost Effectiveness Analysis and WFD economics update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Preliminary Cost Effectiveness Analysis and WFD economics update Kevin Andrews

  2. pCEA - Aim • To minimise the amount of new cost-effectiveness analysis that is needed by drawing on existing information, expertise and processes, • To maximise the amount of analysis done at the national level

  3. pCEA - scope • Scale and nature of problem • Quantum of costs • Affordability • Sectoral shares • Phasing • Uncertainty • Simplification/guidance

  4. Governance Policy Team

  5. Working Groups • Sector working groups • Water industry (Ofwat) • Industry (DTI) • Non-Ag-Diffuse (Defra) • Flood management and planning (Defra) • Navigation and Ports • Cross sector groups • Water resources (EA) • Nutrients (Defra) • Groundwater quality (Defra)

  6. Progress • All sector groups are up and running • Key inputs to information notes drafted • Strategic assessment • Reference cases • Scenarios • Standards • First round of supporting research commissioned

  7. WFD Economics Update

  8. CRP projects status • Project 1 – scoping – completed. Now being operationalised within the EA • Project 2a/b – CEA methodology – completed. • Projects 2c/e - CEA guidance – completed – database and guidance – Being used in pCEA • Project 2d – Cost proformas - completed but untested in E&W – Being used in pCEA • Project 3 – Evidence for DC – DFR – expected to complete in March – still problems

  9. Ongoing work • Project 4 benefits – appointed project manager - agreed strategic approach • Estimate overall benefits for first plan (envelope) + tools for prioritisation + limited empirical work where needed • Improve science/economics for 2nd RBP: • Water body use an access • Integration of science and economics

  10. Choice experiment • Large sample, face to face • Series of survey questions, prompts, reminders, background facts • Choice cards showing different combinations of: • Objective achievement for different water bodies, timings, certainty • Costs • Econometrics can tell you how much people on average are willing to pay for different improvement scenarios

  11. Progress so far • Completed literature review – few previous examples – but very useful • Completed first round of deliberative research groups • Supporting science work underway – draft descriptors developed • Options for survey design being discussed

  12. Expected use of results • Revision of the overall RIA (summer) • Input into SWMI consultation • Guidance for the EA on CEA and DCA

More Related