1 / 20

Inventory Presentation to VFR Regional Management Team July 2001

Inventory Presentation to VFR Regional Management Team July 2001. Regional TEM and VRI Status and Issues Arrowsmith TSA Inventory Update Audit IKONOS Satellite Imagery Assessment. Regional TEM and VRI Summary. Baseline Inventories. TRIM base mapping Cadastre/Ownership

tab
Télécharger la présentation

Inventory Presentation to VFR Regional Management Team July 2001

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Inventory Presentation to VFR Regional Management TeamJuly 2001 Regional TEM and VRI Status and Issues Arrowsmith TSA Inventory Update Audit IKONOS Satellite Imagery Assessment

  2. Regional TEM and VRI Summary

  3. Baseline Inventories • TRIM base mapping • Cadastre/Ownership • Vegetation (VRI) or Forest Cover • Terrestrial Ecosystem Mapping (TEM)

  4. Vegetation Resources Inventory • Replaces traditional forest cover inventory • Comprised of Estimation (Phase 1) and Sampling (Phase 2) • Incorporates measures of statistical accuracy • Initial projects started in 1995:Fraser TSA (Boston Bar) and TFL 25 (Jordan River)

  5. Vegetation Resources Inventory • VRI program currently supported solely by FRBC via major licensee MYA funding • Phase 1 estimation costs ~ $1.50/ha. -similar cost to forest cover interpretation • Phase 2 sampling costs ~ $300,000 per typical management unit (TSA or TFL) • Total VRI cost for a 400,000 ha. mgmt unit ~ $900,000

  6. VRI Completion (Phase 1 and/or 2)

  7. Full VRI Completed -TSA/TFL

  8. VRI Coverage: TSA and TFL

  9. Areas with no VRI • Soo, Sunshine Coast (no Phase 1), Arrowsmith, Strathcona, Mid Coast and QCI TSAs • All Weyerhaeuser and TimberWest TFLs • Interfor - TFL 10, TFL 38 • WFP - TFL 19, TFL 25 (3 Blocks) • Most Provincial/Federal Parks

  10. Possible VRI Priorities for TSAs • Over the next 5 years, at a minimum, should try to complete:- Kingcome TSA (Phase 2) - Mid Coast TSA (Phase 1 and 2)- QCI TSA (Phase 1 and 2) • To achieve this requires total funding of about $3 million - need for a steady yearly budget of at least $500,000

  11. Terrestrial Ecosystem Mapping • TEM is a site series inventory - the step below the Biogeoclimatic Ecosystem Classification (BEC) level • Ecological framework for forest management decisions • Key data source for LU plans, wildlife habitat mapping, site productivity/site index adjustments (SIBEC), silviculture investment strategies, etc. • FRBC is sole funding source for TEM

  12. Current TEM status • TEM and other ecosystem mapping covers about 30% of VFR • More than 90% of TFLs have TEM or other forms of ecosystem mapping • Less than 10% of the TSA area has TEM • Soo, Sunshine Coast, Mid Coast and QCI TSA have no TEM • Fraser, Strathcona and Kingcome TSAs approaching 20% completion • Arrowsmith TSA will be complete by 2003

  13. TEM Coverage in VFR

  14. TEM Coverage by TSA/TFL

  15. TSA Coverage of TEM

  16. TFL Coverage of TEM

  17. TEM Coverage - TSA Areas on Vanc. Island and South Mainland

  18. TEM Issues • Expensive type of inventory - between $2 and $4/ha. • Limited amount of qualified contractor capacity on the Coast • Before 2000, licencees spent all TEM funding from FRBC on their TFLs • Interfor and Canfor are now funding TEM in Kingcome and Strathcona TSAs • MOF receives only $150,000 annuallyfrom FRBC for TEM

  19. The TEM Challenge • Bring TEM on the TSAs up to the same completion level as TFLs • Secure sufficient funding to complete TEM, at least for the productive forested areas - approx. $750,000 annually over 5 years • Co-ordinate TEM projects across the Region to minimise costs/maximise efficient use of resources - a key role for MSRM

  20. The Costs of Not Doing TEM • Vital baseline inventory missing - prevents derivation of other important data, e.g. wildlife habitat suitability • No site productivity adjustments - further downward pressure on AACs • No certification of operations as claims of sustainability rely on ecological inventory - loss of credibility and markets • Key data for land management decisions is missing

More Related