1 / 42

Concrete Test Section

Concrete Test Section. RPF 8 May 2002. Outline. Objectives Design details Material properties Instrumentation Traffic Construction Conclusion. Objectives. To calibrate cncRisk at the lower end of the traffic spectrum To quantify failure of low-volume concrete pavements. Parties.

temira
Télécharger la présentation

Concrete Test Section

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Concrete Test Section RPF 8 May 2002

  2. Outline • Objectives • Design details • Material properties • Instrumentation • Traffic • Construction • Conclusion

  3. Objectives • To calibrate cncRisk at the lower end of the traffic spectrum • To quantify failure of low-volume concrete pavements

  4. Parties • Cement and Concrete Institute • CSIR Transportek • University of Pretoria • Alpha Stone and Readymix • BKS • Raubex

  5. Design details • University of Pretoria • Section 1 • 75 mm SFRC (30 kg/m3) Joint spacing 3 m • 140 mm Foam concrete subbase • In situ • Section 2 • 75 mm SFRC (30 kg/m3) Joint spacing 6 & 4 m • 125 mm CTS • In situ

  6. Design details • University of Pretoria (cont) • Section 3 • 75 mm SFRC (30 kg/m3) No joints • 25 mm ETB • 125 mm CTS • In situ

  7. Design details • CSIR Transportek • Section 4 • 50 mm “CRCP” • 50 mm ETB • 125 mm CTS • In situ • Section 5 • 75 mm “CRCP” • 25 mm ETB • 125 mm CTS • In situ

  8. Design details • CSIR Transportek • Section 6 • 100 mm “CRCP” • 125 mm CTS • In situ

  9. Design details • C&CI • Section 7 • 100 mm butt jointed Joint spacing 2 and 3 m • 125 mm CTS • In situ • Section 8 • 100 mm butt jointed Joint spacing 2 and 3 m • 40 mm continuously graded asphalt • 100 mm CTS • In situ

  10. Design details • C&CI • Section 9 • 140 mm jointed Joint spacing 2, 3 and 4 m • 125 mm gravel • In situ • Section 10 • 140 mm butt jointed Joint spacing 2, 3 and 4 m • 125 gravel • In situ

  11. Design details • C&CI • Section 11 • 140 mm dowel jointed Joint spacing 2, 3 and 4 m Dowels 25 mm @ 300 c/c • 125 mm gravel • In situ

  12. Material Properties • In situ • CBR 80 • Quartzitic gravel A-1-a G5/G6 • Compaction 97% Mod. AASHTO • FWD deflections  1,0 mm

  13. Material Properties • Subbase • As in situ • Compaction 97% Mod. AASHTO • Stabilized with 2% CEM I 42.5 (C3) (Recycler) • UCS  2000 kPa • FWD deflection 0,9 mm and Stab 0,5 mm

  14. Material Properties • ETB • Subbase material • Stabilized with 1,5% anionic stable grade 60%, 1% cement • Asphalt • Continuously graded hot mix with 60/70 pen • 12 mm aggregate size

  15. Material Properties • Concrete • Strength • fc 22 - 42 MPa • ff 3,7 - 5,6 MPa • Mod E 24 - 33 GPa • Shrinkage 0,05 - 0,06 % • Cement CEM I 42,5/GGBS 80/20

  16. Instrumentation • LVDT’s • Centre • Side • Thermocouples • Conventional • Programmable • MDD’s • Weather station

  17. Construction • Readymix concrete • Compaction by poker and beam • Curing compound • Plastic sheeting

  18. Traffic • Trucks leaving quarry • Weighbridge data • No of axles • Approximately 300 E80’s per day • To date 14 000 E 80’s

  19. Observations • Very little distress to date • Vertical movement at joints under traffic but no relative movement • Rocking of slabs on foam concrete • Some corner breaks • Plastic shrinkage cracks not affecting performance

  20. Future • Ongoing observations • Continual recording of instruments to end May • Panel to define failure • Analysis of results • Availability of data

  21. Thank you

More Related