Marina Reservoir Recirculation Scheme (MRRS). Project Status Consultants: CDM Detailed Design stage Scope of construction works Discharge structures & pipelines Pumping facility and pipeline Modification of existing Waterworks Spillway and channels.
E N D
Marina Reservoir Recirculation Scheme (MRRS) • Project Status • Consultants: CDM • Detailed Design stage • Scope of construction works • Discharge structures & pipelines • Pumping facility and pipeline • Modification of existing Waterworks • Spillway and channels
Marina Reservoir Recirculation Scheme (MRRS) Tenders Schedule 1. Construction of Discharge Structures for Eastern & Central Pipelines Expected Tender Calling Date : Jul 2008 2. Construction of Pumping Facility and Pipeline near Whampoa Canal Expected Tender Calling Date : Aug 2008 3. Construction of Spillway and Channels at Upper Pierce Reservoir Expected Tender Calling Date : Sep 2008 4. Modification of Chestnut Avenue Waterworks Expected Tender Calling Date : Oct 2008