1 / 11

ME1/1 ODMB Production Readiness Review: Schedule and Budget

ME1/1 ODMB Production Readiness Review: Schedule and Budget. Darien Wood Northeastern University For the ME1/1 Electronics Project. Categories. On-chamber electronics DCFEBs (504 + spares) LVDB (72+) LVMB (72+) ALCT mezz (72+) Peripheral crate electronics OTMB mezz (72+)

umed
Télécharger la présentation

ME1/1 ODMB Production Readiness Review: Schedule and Budget

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ME1/1 ODMB Production Readiness Review: Schedule and Budget Darien Wood Northeastern University For the ME1/1 Electronics Project

  2. Categories • On-chamber electronics • DCFEBs (504 + spares) • LVDB (72+) • LVMB (72+) • ALCT mezz (72+) • Peripheral crate electronics • OTMB mezz (72+) • OTMB base boards (72+) • ODMB (72+) • Infrastructure • New LV supplies, junction boxes, cables supply to JB • Patch panels • Peripheral crate modification • Optical cables • Signal cables (pads to DCFEB – 40% new)

  3. Where we are today • DCFEB: • Production and testing >50% complete • Expect final production run in ~3 weeks • 14 boards installed in detector in 2 “demonstrator chambers” • OTMB • Mezzanine: production and testing complete • Base board – production fabrication underway, all parts in hand • 2 production mezzanines with old base boards installed temporarily for demonstrators • ODMB • First prototype (2012) • Only designed for optical TTC (anticipating FF_EMU ASIC, since abandoned) • Limited capability for interfacing with DCFEB, but able to read out optical data path • Second prototype (April 2013) • Fully functional design • Boards at UCSB, OSU, Rice and CERN • Used for some STEP tests for testing chambers after refurbishing • Used to read out 2 demonstrator chambers • Preproduction starting (10 boards, production design)

  4. ME1/1 Installation Schedule • Selected items from TC1 schedule (11-Sep-2013) • ODMB boards go into Peripheral VME crates • Do not have the installation constraints of on-chamber electronics • While waiting for final ODMB production, use prototype v2 boards and preproduction boards for commissioning • Have 10 v2 boards, making 10 pre-production boards

  5. ODMB pre-production and final production • Production procurement was begun on 27-Aug • Expect complete parts Nov-Dec • Parts for 10 preproduction boards should be in hand next week • Used alternate source for smaller quantity of FPGA’s • Want pre-production board at CERN as soon as possible • Commissioning • Long Term Test Stand

  6. Schedule elements • October 10: All components for first 10 boards delivered to Pactron. • October 11: Begin production of first 10 boards. • November 1: First 10 boards arrive at UCSB. • November 8: First 5 boards tested at UCSB, some shipped to CERN. • November 15: Boards 5-10 tested at UCSB, more shipped to CERN. • November 8: All components delivered to Pactron. • December 1: Begin production of remaining 80 boards. • January 1: Remaining boards begin arriving at UCSB. • February 1: Finish production testing of boards at UCSB

  7. Schedule risks • Delay in delivery of parts (08 Nov → 08 Dec) • Lost time over Dec/Jan holidays • Production start → 10 January • Production testing slower than assumed (4/day → 2/day)

  8. Schedule elements with pessimistic assumptions • October 10: All components for first 10 boards delivered to Pactron. • October 11: Begin production of first 10 boards. • November 8: First 10 boards arrive at UCSB. • November 21: First 5 boards tested at UCSB, ship some to CERN. • December 1: Boards 5-10 tested at UCSB, more shipped to CERN. • December 8: All components delivered to Pactron. • January 10: Begin production of remaining 80 boards. • February 10: Remaining boards begin arriving at UCSB. • March 20: Finish production testing of boards at UCSB.

  9. ODMB cost details 72 boards + 18 spares = 90 boards Single costs (setup, testing, shipping): $ 3750 Test equipment: $7500 Cost increment for first 10 boards: $2900 (may be a bit more) Total production cost estimate: $220k (includes pre-production) Estimate from July 2013 change request: $234 k

  10. Backup Slides

  11. Peripheral crate for demonstrator chambers

More Related