1 / 27

Estimates Update Training Bulletins for 2013

Estimates Update Training Bulletins for 2013. Melissa Hollis, Basis of Estimates Coordinator August 1, 2013 webinar. Agenda. July 2013 changes (10 min) COPS issues covered at Design Expo Brief Review of remaining issues January 2014 changes COPS issues (10 min)

vilina
Télécharger la présentation

Estimates Update Training Bulletins for 2013

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Estimates Update TrainingBulletins for 2013 Melissa Hollis, Basis of Estimates CoordinatorAugust 1, 2013 webinar

  2. Agenda • July 2013 changes (10 min) • COPS issues covered at Design Expo • Brief Review of remaining issues • January 2014 changes • COPS issues (10 min) • Specs and Standards issues (20 min) • Legal and Administrative (10 min) • Questions/Answers(10 min)

  3. Implementation Schedule • Posted Dates • December 2012 to May 2013 • Letting Dates • July to December 2013 • “July workbook” and 2013 e-book • Posted Dates • July 2013 • Letting Dates • January to June 2014 • “January workbook” and 2014 e-book

  4. Types of Changes • COPS: Consolidation of Products and Specifications • Minimum Specifications for Traffic Control Signals and Devices (MSTCSD) • Approved Products List (APL) • Qualified Products List (QPL) • Specifications or Design Standards • Legal or Contract Administration

  5. July-December 2013 lettings • COPS • 12-12: Consolidation of Products and Specifications (COPS) • 12-14: Jack & Bore for Drainage • 12-15: Conduit and related changes • 12-17: Vehicle Detectors • 12-18: Communication Cable • 12-19: Pull, Splice, and Junction Boxes “A box is a box” The same products are used by lighting, signals, and ITS

  6. July-December 2013 lettings • Specification changes • 12-16: Asphalt Binders • 12-20: Litter and Mowing Binder selection: Coordinate with the District Pavement Design Engineer Litter Areas: edge of pavement to R/W line include established landscape beds, if accessible exclude new landscape beds (included under 580) Mowing Areas: grass/sod areas to R/W line exclude inaccessible areas, woods, ponds, landscape beds BOTH: 30 day cycle. NO variations for season, location, etc. payment will be adjusted for actual areas and cycles

  7. July-December 2013 lettings • Legal or Administrative • 12-13: Mobilization and Maintenance of Traffic- Multiple Locations LS pay item • 12-21: 2013 Master File "Pay Item Year” fuel factors • 13-01: Security of the Official Estimate (PES/CES changes for Estimators) Internal security • 13-02: Comp Book and Quantity Computation Documents (for lump sum projects) Distribution Process CPR: all bidders • 13-03: Landscape and Related Work CPR: accounting • 13-04: Lump Sum and Special Design Pay Items on Pushbutton Contracts Defined work for bidding

  8. January 2014 lettings • COPS changes • 13-12: Intersection Control Beacon • Flashing signal at an intersection • Pay item description changed from “Flashing Beacon Controller” to “Intersection Control Beacon” • Not for use with signs

  9. January 2014 lettings • COPS changes • 13-13: Pedestrian Detectors • Standard or Accessible • Pole, post, or pedestal paid separately (no station) • 641 Prestressed Concrete Pole • 646 Aluminum Signals Pole (including pedestrian station post) • 649 Steel Strain Pole or Mast Arm Assembly

  10. January 2014 lettings • 13-08: Midblock Crossing • In-Roadway lights • 1 assembly includes lights, detectors, signs, cabinet, electronics • RRFB: Rectangular Rapid Flashing Beacon Assembly • 1 assembly includes “everything on the post”: beacons, signs, cabinet, electronics, wiring, pedestrian detector • Single sided or back-to-back • 2, 3, or 4 assemblies per crossing • Pedestrian Hybrid Beacon Assembly • 1 assembly includes just the 3-section signal with backplate • Minimum of 2 signals per approach (4+ assemblies per crossing) • Separate payment for poles, detectors, cabinet, etc.

  11. Mid Block Crossing examples • Assembly, by type Pay Item structure: option for AC or solar power on 654-1 and 654-2.

  12. January 2014 lettings • Specification Changes • 13-07: Sidewalk, Curb Ramps, and Detectable Warnings • 520- Curb (various types) • 522- Sidewalk and Driveways (includes ramps) • Removal is included in cost of new sidewalk • 527- Detectable Warnings • Old: no payment for new / each payment for retrofit • New: Square foot payment for all • Tabulate each location in the plans • Refer to Index 304 for estimated quantities • Same for Construction and Maintenance

  13. Index 304, sheet 7 of 7

  14. January 2014 lettings • Specification Changes • 13-11: Highway Signing • Sheeting requirements updated (reflectivity) • Added various types of electronic signs • Separated panels, structures, and beacons • Consistent pay item structure between items More on each pay item group…

  15. January 2014 lettings • Specification Changes • 13-11: Highway Signing • 700-1-AB Single Post Sign, per assembly • 700-2-AB Multi Post Sign, per assembly • Includes sign panel(s), post(s), foundation • B= sheeting area of all panels, NOT wind load area • B=0 for relocate, remove, repair • Barrier Mount: Index 11871, max 20 sf wind load area • Bridge Mount: Index 11870, max wind load on index

  16. Sign Assembly 1 assembly (all 6 panels and post) 1 assembly (all panels and 2 posts)

  17. January 2014 lettings • 13-11: Highway Signing • 700-3-ABB Sign Panel, each • Complete message • Can be used to add a panel to an existing post/structure • DO NOT USE for additional panels on a new assembly • 700-4-ABC Overhead Static Sign Structure, each • Static Signs only; DMS sign structures paid under 700-10 • Sign panels paid under 700-3

  18. Static Sign Support Structure 700-4-ABC B=2 Span 700-4-ABC B=1 Cantilever 700-4-ABC B=4 Bridge Mount, C=0

  19. January 2014 lettings • 13-11: Highway Signing • 700-5-AB Internally Illuminated Sign, per each • Includes street name signs • Mounted on span wire or mast arm • Support structure paid separately • Maximum 18 sf, per specification

  20. January 2014 lettings • 13-11: Highway Signing • 700-6-AB Highlighted Sign, per assembly • Similar to single post assembly • AC or solar powered • Includes cabinet, LEDs, sign, post, foundation • Need for visibility, cost, maintenance- MUTCD

  21. January 2014 lettings • 13-11: Highway Signing • 700-7-ABC Embedded Dynamic Message Sign, per each • Embedded sign only; static sign support/assembly paid separately • 700-8-ABC Front Access Dynamic Message Sign, per each • May be included with a static sign, or used alone • 700-9-ABC Walk-in Dynamic Message Sign, per each • 700-10-ABC Dynamic Message Sign Support Structure, per each • Single Post, Multi-post, overhead bridge mount: Front access signs • Span, Cantilever: Walk-in signs

  22. Dynamic Message Sign examples Front Access sign examples 2 embedded signs 1 sign panel 1 static sign support structure Walk-in sign, DMS sign support structure

  23. January 2014 lettings • 13-11: Highway Signing • 700-11-ABC Electronic Display Sign, per assembly • “everything on the post” assembly: Includes the sign(s), support structure, foundation, cabinet, speed detector • “integrated dynamic display” • AC or solar powered; with/without sign beacons • Ground or overhead mounted- depending on type

  24. January 2014 lettings • 13-11: Highway Signing • 700-12-AB Sign Beacon, per assembly • Intended for adding beacon(s) to static signs • Sign assemblies are paid separately • AC or solar powered • 1 or 2 beacons

  25. January 2014 lettings • Administrative Issues • 13-06: Crash Cushions • No separate payment for repairs. Changes to Section 7- Protection of existing property, 3rd party damages • 13-09: Replacement of Computation Books with Plan Summary Boxes • Webinar for CADD/Designers • Webinar for Estimators/Reviewers • Webinar for CEI/Construction Final Estimates

  26. January 2014 lettings • Administrative Issues • 13-10: Landscaping PENDING • Engineering & Operations Memo from March 2013 is still in effect. • Guidelines are pending for • Contract Type • Specs • Performance Bond • Pay Items • Funding • Coordination • Contract Administration

  27. Questions/Comments • Pay Items or BOE details Melissa Hollis, BOE Coordinator Melissa.Hollis@dot.state.fl.us • Guidelines/Handbooks • Specifications • Technical questions • CADD or documentation issues • Design Standards • Construction issues