1 / 15

Minuteman Vocational Technical Regional High School Progress

Minuteman Vocational Technical Regional High School Progress. May 20 th 2019 – June 17 th 2019. June 17 th View of Area A+B – Upper Level Bathroom finishes substantially complete; toilet partitions, accessories and fixtures. June 17 th View of Area A+B – Lower Level

vivi
Télécharger la présentation

Minuteman Vocational Technical Regional High School Progress

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Minuteman Vocational Technical Regional High School Progress May 20th 2019 – June 17th 2019

  2. June 17thView of Area A+B – Upper Level Bathroom finishes substantially complete; toilet partitions, accessories and fixtures. June 17thView of Area A+B – Lower Level Flooring materials substantially complete. Testing and Balancing of Mechanical Equip in progress.

  3. June 17thView of Area G – Exterior Both Greenhouses in progress with exterior wall and roof glass installation.

  4. June 17thView of Area D – Upper Level Typical classroom on floor substantially complete June 17thView of Area D – Lower Level Ceramic wall tile substantially complete. Ceiling grid in progress, MEP devices to follow.

  5. June 17thView of Area D – Gymnasium Wood Gym floor court lines and logos complete. Final coats of sealer in progress, vented base installation to commence Wednesday.

  6. June 17thView of Area E – Upper Level Skylight openings complete and painted. June 17thView of Area E – Upper Level Ceiling tile installation in Media Center complete. VCT Flooring in classrooms & offices complete.

  7. June 17thView of Area E+F – Cafeteria Painting substantially complete. Ceiling tile installation in progress. Ceramic wall tile in progress

  8. June 17thView of Area F – Lower Level Millwork installation in progress. Plumbing fixtures installation in progress. Epoxy floor in Kitchen complete. Setting of Kitchen Equipment in progress.

  9. June 17thView of Area C – Theater Installation of fire curtain system complete. Counterweight rigging system in progress. June 17thView of Area C – Band & Chorus Millwork & Casework installation complete. VCT Flooring installation in progress.

  10. June 17thView of Area A+B – West Roadway Loam and seed of drainage swale complete. Perimeter roadway asphalt binder complete.

  11. June 17thView of Faculty Parking Lot - South Asphalt binder complete. Setting of curb & concrete sidewalk placement in progress.

  12. June 17thView of Faculty Parking Lot–North Asphalt binder complete. Setting of curb & concrete sidewalk placement in progress.

  13. June Construction Schedule Look Ahead: Area A+B & G • Complete Testing & Balancing of Mechanical Units – Area A+B Remain, Area G completed as of this update • Complete Concrete Sealant of Shop Floors • Continue Punchlist Process Area D • Complete floor finish on Gymnasium floor • Commence Wall Pad, Bleachers and Scoreboard installation • Commence Testing & Balancing of Mechanical Units. Unit feeding the Gymnasium previously completed • Commence Punchlist process Area E • Complete Classroom/Office Flooring Installation on Lower Level • Complete Millwork installation in Media Center and Lower Level • Commence Corridor flooring Installation on Upper & Lower Level Area F • Complete Installation of Ceramic Wall Tile • Complete with installation of Millwork • Continue with installation & connections of Kitchen equipment Area C • Complete Mechanical Hoist Rigging Installation • Complete Flooring activities in Band & Chorus Area • Continue Counterweight & Guidewall Rigging Installation • Commence Testing & Balancing of Mechanical Unit that feeds Band & Chorus Exterior/Sitework • Continue installation of granite curbing in faculty parking lot • Continue with placing concrete sidewalks and speed tables • Continue with landscaping plantings at perimeter of site • Continue with fill & utility installation in the Student parking lot

  14. Project Turn-Over Schedule Look Ahead:

More Related