This chapter explores crucial aspects of project management, focusing on the behavioral dynamics of project personnel and managers. It highlights the significance of the Work Breakdown Structure (WBS) in organizing project activities and offers insights on PERT/CPM techniques for effective project scheduling. You will learn to construct network diagrams, analyze deterministic networks, and understand project crashing mechanisms. Key elements include the project life cycle, triple constraints of time, cost, and scope, along with essential skills for project managers that drive project success.
E N D
Chapter 17 Project Management
Learning Objectives • You should be able to: • Discuss the behavioral aspects of projects in terms of project personnel and the project manager • Explain the nature and importance of a work breakdown structure in project management • Give a general description of PERT/CPM techniques • Construct simple network diagrams • List the kinds of information that a PERT or CPM analysis can provide • Analyze networks with deterministic times • Describe activity ‘crashing’ and solve typical problems Instructor Slides
Projects • Project: • Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame • Examples: • The Olympic Games • Producing a movie • Product development • Operations: • work done to sustain the business 17-3
Project Life Cycle 17-4
The Triple Constraint of Project Management • Project’s Triple Constraints (Key Metrics) • Time • Cost • Scope (Performance objectives) • Quality Information Technology Project Management, Sixth Edition
Project Success • There are several ways to define project success: • The project met scope, time, and cost goals • The project satisfied the customer/sponsor • The results of the project met its main objective e.g., making or saving a certain amount of money, providing a good return on investment. Information Technology Project Management, Sixth Edition
Project Manager • Project managers work with the project team and other people involved in a project to meet project goals • The project manager is ultimately responsible for the success or failure of the project • The project manager skills and competencies: • People skills • Leadership • Listening • Integrity, ethical behavior, consistent • Strong at building trust • Verbal communication • Strong at building teams • Conflict resolution, conflict management • Critical thinking, problem solving • Understands, balances priorities 17-7
Project Management • Key tools: • Work Breakdown Structure • Gantt charts • Network diagram
Work Breakdown Structure (WBS) • WBS • A hierarchical listing of what must be done during a project • Establishes a logical framework for identifying the required activities for the project • Identify the major elements of the project • Identify the major supporting activities for each of the major elements • Break down each major supporting activity into a list of the activities that will be needed to accomplish it 17-9
WBS Open new department New facility Finance Staff Hiring Relocating Location Furniture Move in Remodel Locate facility Hire & train Order furniture Furniture setup interview 17-10
Critical Path Method (CPM) • CPM can assist in: • estimating project length • Identifying which activities are most critical to timely project completion • indicating of how long any activity can be delayed without delaying the project 17-11
Network Diagram • Network diagram • (Precedence) Diagram of project activities that shows sequential relationships by use of arrows and nodes • Activity on arrow (AOA) • Network diagram convention in which arrows designate activities • Activity on node (AON) • Network convention in which nodes designate activities 17-12
b a a c b c a c a c d b dummy Node b Network Conventions (AON) (dummy) Start Node
a b c a c b a c a c dummy Activity b b d Network Conventions (AOA)
Project Network – Activity on Node (AON) Orderfurniture 2 Furnituresetup Locatefacilities 6 1 Move in Remodel S 5 7 Hire andtrain Interview 4 3
Project Network – Activity on Arrow (AOA) Orderfurniture Furnituresetup Locatefacilities Remodel Move in Interview Hire andtrain
Gantt Chart 17-18
Critical Path Method (CPM) 9-19 • An analytical tool that provides a schedule that completes the project in minimum time subject to the precedence constraints. • In addition, CPM provides: • Starting and ending times for each activity • Identification of the critical activities (i.e., the ones whose delay necessarily delay the project). • Identification of the non-critical activities, and the amount of slack time available when scheduling these activities.
Network Diagram (cont’d) • Path • Sequence of activities that leads from the starting node to the finishing node • Critical path • The longest path; determines expected project duration • Critical activities • Activities on the critical path • Slack • Allowable slippage for a path; the difference the length of path and the length of critical path
Project Network – Activity on Node (AON) Critical Path ? Orderfurniture 2 Furnituresetup Locatefacilities 6 1 Move in Remodel S 5 7 Hire andtrain Interview 4 3
Gantt Chart Critical Path ? 17-22
Example 6 3 B C 8 A 11 1 D S G 4 9 E F
Early Start, Early Finish • Early start (ES) • The earliest time an activity can start • Assumes all preceding activities start as early as possible • For nodes with one entering arrow • ES = EF of the entering arrow • For activities leaving nodes with multiple entering arrows • ES = the largest of the entering EF • Early finish (EF) • The earliest time an activity can finish • EF = ES + t • Finding ES (Early Start) and EF (Early Finish) involves a forward pass through the network diagram 17-24
Example – Forward pass (ES, EF) 6 8 14 3 14 17 B C 8 8 0 A 11 8 19 0 1 0 0 19 D 20 S G 4 4 9 0 13 4 E F
Late Start, Late Finish • Late Finish (LF) • The latest time the activity can finish and not delay the project • For nodes with one leaving arrow, LF for nodes entering that node equals the LS of the leaving arrow • For nodes with multiple leaving arrows, LF for arrows entering node equals the smallest of the leaving arrows • Late Start (LS) • The latest time the activity can start and not delay the project • The latest starting time for each activity is equal to its latest finishing time minus its expected duration: • LS = LF - t • Finding LS and LF involves a backward pass through the network diagram 17-26
Example – Backward pass (LS, LF) 16 10 16 19 8 6 14 14 3 17 B 0 C 8 0 8 8 A 19 8 0 0 19 20 8 11 19 0 0 0 19 1 20 D S G 6 10 10 19 0 4 4 4 9 13 E F
Slack and the Critical Path • Slack can be computed one of two ways: • Slack = LS – ES • Slack = LF – EF • Critical path • The critical path is indicated by the activities with zero slack 17-28
Example – Slack (LS-ES,LF-EF) 10 16 8 6 14 2 16 19 14 3 17 2 B 0 8 0 8 8 0 C 8 19 8 11 19 0 A 19 20 0 0 0 0 19 1 20 0 0 0 D S G 6 10 0 4 4 6 10 19 4 9 13 6 E F
Example – Critical Path Slack (LS-ES;LF-EF)=0 2 2 B C 0 A 0 0 0 D S G 6 6 E F
Example Solution Critical Path
Using Slack Times • Knowledge of slack times provides managers with information for planning allocation of scarce resources • Control efforts can be directed toward those activities that might be most susceptible to delaying the project • Activity slack times are based on the assumption that all of the activities on the same path will be started as early as possible and not exceed their expected time • If two activities are on the same path and have the same slack, this will be the total slack available to both 17-32
The Critical Path Method (CPM) is not useful for (Multiple Choices Question): • Finding the project’s shortest completion time • Finding the project’s minimum cost • Calculating start and end times for all activities • Identifying critical activities • Identifying the slack for non-critical activities
Time-Cost Trade-Offs • Activity time estimates are made for some given level of resources • It may be possible to reduce the duration of a project by injecting additional resources • Motivations: • To avoid late penalties • Monetary incentives • Free resources for use on other projects 17-34
Time-Cost Trade-Offs: Crashing • Crashing • Shortening activity durations • Typically, involves the use of additional funds to support additional personnel or more efficient equipment, and the relaxing of some work specifications • The project duration may be shortened by increasing direct expenses, thereby realizing savings in indirectproject costs
Crashing Activities 17-36
Crashing Decisions • To make decisions concerning crashing requires information about: • Time: • Regular time and crash time estimates for each activity • Cost: • Regular cost and crash cost estimates for each activity • A list of activities that are on the critical path • Critical path activities are potential candidates for crashing • Crashing non-critical path activities would not have an impact on overall project duration 17-37
Crashing: Procedure • General procedure: • Crash the project one period at a time • Crash only activities on the critical path/s • Crash the least expensive activity (that is on the critical path) • When there are multiple critical paths, find the sum of crashing the least expensive activity on each critical path • If two or more critical paths share common activities, compare the least expensive cost of crashing a common activity shared by critical paths with the sum for the separate critical paths 17-38
10 b 6 a 2 f 5 c 9 e 4 d Example 7
10 b 6 a 2 f 5 c 9 e 4 d 1. Determine Critical Path PathLength a-b-f 18 c-d-e-f 20 (critical path) 2. Rank activities on CP in order of lowest crashing cost ActivityCost per day to crashAvailable days c 300 1 e 600 2 d 700 3 f 800 1
10 b 6 a 2 f 5 c 9 e 4 d 2. Rank activities on CP in order of lowest crashing cost ActivityCost per day to crashAvailable days c 300 1 e 600 2 d 700 3 f 800 1 Crash activity c by 1 day: cost $300 < $1,000 (CP=19 days) (cannot crash c anymore) 5 4
10 b 6 a 2 f 5 c e 4 d Crash activity e by 1 day: cost $600 < $1,000 (CP=18 days) (may crash activity e by 1 more day) 2. Rank activities on CP in order of lowest crashing cost ActivityCost per day to crashAvailable days c 300 1 e 600 2 d 700 3 f 800 1 4 8 9 • Bothpaths are now critical. • Have to crash both in order to shorten project.
10 b 6 a 2 f 4 c 8 e 4 d Both paths are now critical. Have to crash both in order to shorten project. Remaining activities PathActivityCost per day to crashAvailable days a-b-f a - - b 500 2 f 800 1 c-d-e-f c - - e 600 1 d 700 3 f 800 1 Crash activity f (is on both paths) by 1 day: cost = $800 < $1,000 (CP=17 days)
10 b 6 a 1 f 4 c 8 e 4 d Crash activity f (is on both paths) by 1 day: cost $800 < $1,000 (CP=17 days) Remaining activities PathActivityCost per day to crashAvailable days a-b-f a - - b 500 2 f 800 1 c-d-e-f c - - e 600 1 d 700 3 f 800 1 2
10 b 6 a 1 f 4 c 8 e 4 d Both paths are still critical. Have to crash both in order to shorten project. Remaining activities PathActivityCost per day to crashAvailable days a-b-f a - - b 500 2 f-- c-d-e-f c - - e 600 1 d 700 3 f-- Crash activity b by 1 day: cost $500 AND Crash activity e by 1 day: cost $600 Total cost: $1,100>$1,000 (indirect costs) =>DONE!
Length after crashing Path\crashn=0 1 2 3 a-b-f 18 18 18 17 c-d-e-f 20 19 18 17 Activity Crashed c e f Cost 0($300)($600)($800) Savings 0 $1,000 $1,000 $1,000 Total 0 $700 +$400 +$200 = $1,300
Operations Strategy* • Projects present both strategic opportunities and risks • It is critical to devote sufficient resources and attention to projects • Projects are often employed in situations that are characterized by significant uncertainties and risks that may result in: • Delays • Budget overruns • Failure • PM should use: • Careful planning • Wise selection of project manager and team • Monitoring of the project • It is not uncommon for projects to fail • it is beneficial to examine the reasons for failure – “lessons learned” 17-48