zenia
Uploaded by
9 SLIDES
234 VUES
90LIKES

Facility Forward A Facility Restructuring Design

DESCRIPTION

The Indiana Department of Correction, under Commissioner Edwin G. Buss, is implementing a comprehensive strategy to enhance facility capacity and efficiency. Current capacity shows shortfalls across multiple security levels, with significant utilization rates exceeding 99%. This project aims to maximize existing facilities, achieving projected savings of $186 million by efficiently managing resources, minimizing utility costs, and consolidating operations. Key initiatives include relocating Indianapolis Parole, co-locating PEN Products, and selling the IMWR facility. The anticipation is to delay the need for new construction while improving services for offenders.

1 / 9

Download Presentation
Télécharger la présentation

Facility Forward A Facility Restructuring Design

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Facility Forward A Facility Restructuring Design Indiana Department of Correction Edwin G. Buss, Commissioner

  2. Preparing Indiana For Today, Tomorrow, & Beyond Strategically & Successfully

  3. Current Capacity Shortfalls • Minimum Security • -Available Beds = 60 • -Capacity = 96.1% • Low Medium Security • -Available Beds = 129 • -Capacity = 99.1% • High Medium Security • -Available Beds = 29 • -Capacity = 99.4% • Maximum Security • -Available Beds = 26 • -Capacity = 99.5% • All Male Facilities • -Available Beds = 220 • -Capacity = 99.1% • All Female Facilities • -Available Beds = 54 • -Capacity = 97.8%

  4. Facility Forward At A Glance

  5. Managing Capacity Throughout the Agency

  6. Projected Savings Overall Projected Savings = $186M • More efficient utilization of current facilities increases bed capacity; therefore, delays the need to build a new facility • Elimination of lease and utility expenses • Co-locate PEN Products to the Randolph Street location • Indianapolis Parole relocated to Downtown locations • Sale of IMWR Facility • Elimination of utility costs for both IMWR and IWWR • Elimination of transportation of 2,000+ offenders annually

  7. Why STOP?

  8. Anticipated Timelines

  9. Madison Juvenile Correctional Facility