1 / 13

Construction (Design and Management) Regulations 2007 Overview

Construction (Design and Management) Regulations 2007 Overview. Version: September 07. Overview of the construction industry. Output - 8% of UK GDP 1.75M site workers and 450K professionals and consultants (8% of working population) 190,000 companies (95% employ < 10)

zinnia
Télécharger la présentation

Construction (Design and Management) Regulations 2007 Overview

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Construction (Design and Management) Regulations 2007Overview Version: September 07

  2. Overview of the construction industry • Output - 8% of UK GDP • 1.75M site workers and 450K professionals and consultants (8% of working population) • 190,000 companies (95% employ < 10) • Over 200+ key stakeholders • No entry threshold/transitory workplaces • £17bn unofficial economy • Disproportionate level of fatals, major injuries and incidents of ill-health CDM 2007 Overview

  3. Key health and safety statistics • 32% of all worker fatalities (77 killed in 2006/07) • 15% of all major employee injuries (3677 in 2005/06) • 7492 over 3-day injuries to employees (2005/06) • 86,000 suffering from work-related ill health (2005/06) • 3.2M working days lost per year due to injury and ill health (2005/06) CDM 2007 Overview

  4. Fatal and injury trends(Percentage incidence rate changes against targets) CDM 2007 Overview

  5. Background – CDM 94 • Construction (Design & Management) Regulations 1994 implemented key aspects of a construction European Directive • Identified the need to reduce risk by better co-ordination, management and co-operation • For the first time the duties on clients and designers were made more explicit • CDM 94 led to a major change in how the industry managed health and safety CDM 2007 Overview

  6. CDM 94 - Why Change? • Concerns from industry and HSE that CDM 94 was not delivering the improvements in health and safety that were expected of it • Slow acceptance, particularly amongst clients and designers • Effective planning, management, communications and co-ordination less than expected • Competence of organisations and individuals slow to improve • Defensive verification approach adopted by many – led to complexity and bureaucracy CDM 2007 Overview

  7. History of CDM 2007 • Extensive consultation and partnership working between industry and HSE • September 2002 - Discussion Document ‘Revitalising Health and Safety in Construction’ • March 2005 - HSC publish Consultation Document with draft Regulations – which combine CDM 94 and Construction (Health, Safety & Welfare) Regulations 1996 • December 2005 - HSC agreed Regulations should be supported by an Approved Code of Practice and industry produced guidance • CDM 2007 came into force April 2007 CDM 2007 Overview

  8. The objectives of CDM 2007 • Simplify the regulations and improve clarity • Maximise their flexibility • Focus on planning and management, not ‘The Plan’ and other paperwork • Strengthen requirements on co-operation and co-ordination- encourage better integration • Simplify competence assessment, reduce bureaucracy and raise standards CDM 2007 Overview

  9. Structure of CDM 2007 • Five parts • Part 1: Introduction • Part 2: General management duties applying to all construction projects • Part 3: Additional duties where projects are notifiable • Part 4: Worksite health and safety requirements • Part 5: General • Supported by a CDM 2007 Approved Code of Practice (ACoP) CDM 2007 Overview

  10. CDM 2007 – key points • Regulations apply to all construction work • Notification triggers appointment of additional duty holders and duties in Part 3 of the Regulations • Principal contractor (PC) • CDM co-ordinator (role of planning supervisor under CDM 94 has been removed) • Notification to HSE (F10 Form) • Construction phase plan (requirement for pre-construction plan under CDM 94 removed) • Health and safety file • Most duties remain on clients, designers & contractors regardless of notification • Greater clarity in relation to competence assessment and new competence criteria in the ACoP CDM 2007 Overview

  11. Notifiable construction work under CDM 2007 are construction projects with a: Non-domestic client and involve Construction work lasting longer than 30 days or Construction work involving 500 person days Note – Trigger under CDM 94 had been more complex Trigger for Appointments CDM 2007 Overview

  12. HSE’s expectations on the construction industry • A change in attitude is needed to deliver the much needed improvements in construction health and safety • A ‘business as usual’ approach is not acceptable • Industry needs to take ownership of the management of health and safety risks, show leadership and work in partnership • Focus on effective planning and managing risk • Ensure people are competent • Reduce bureaucracy & paperwork CDM 2007 Overview

  13. CDM 2007 – Key messages • Industry and HSE have worked in partnership to revise and simply the CDM Regulations and combine them with the CHSW Regulations • The new regulations apply if you are involved in construction and will help you to improve health and safety in the industry • The aims of the new regulations are to have the right people for the right job at the right time to manage risks on site, reduce paperwork and encourage teamwork • Focus on effective planning and managing risk CDM 2007 Overview

More Related