1 / 9

Effort for Installation and Testing

Effort for Installation and Testing. Attempt to collect information from previous talks… Web shift list has been established (Dave Robinson) http://www.hep.phy.cam.ac.uk/si-bin/sctworkplanner.cgi

acapps
Télécharger la présentation

Effort for Installation and Testing

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Effort for Installation and Testing Attempt to collect information from previous talks… Web shift list has been established (Dave Robinson) http://www.hep.phy.cam.ac.uk/si-bin/sctworkplanner.cgi Natural to extend this pool of ad-hoc SCT shifters to cover future installation testing where little training is needed Also need experts to coordinate (and sometimes do) work I will give very rough estimates of the numbers of shifts, scaling from Sandra’s needs for Type IV Pippa Wells

  2. Type IV cables • Sandra Ciocio and Petr Kubik working full time • Shift list seems to be working for testing • Big problem to organise putting on connectors in situ. • Try the solution of an external company proposed by Marzio Nessi. • Do any SCT institutes have qualified technicians who could come to work at CERN for a few months to make connectors? • Do we appeal to other ID institutes (eg. TRT institutes) • Sandra estimates 600 shifts • These are 3 hour shifts. Two people in a team, so 600 shifts correspond to 150 days. Pippa Wells

  3. PP3 • Shaun Roe and Igor Ilyashenko will do testing at CERN, with help from Pamela Ferrari and Ewa Stanecka for setting up (CERN) • Ashley French (Melbourne) coming on 1 October for installation (for how long?). Occasional help from SR1 technicians for mechanics, when Ashley isn’t here. • Igor will also be available to help with installation. • Tests in situ will add a new task to the list of the cable testers. • Remains to be seen how easily one PP3 card can be swapped, if there is a problem! • Testing PP3 in rack: 200 shifts Pippa Wells

  4. Type II/III cables, dPP1 • Need qualified technicians to install dPP1, and to supervise connector type II end. • Sandra/Piotr should be able to supervise connecting/testing at PP3 racks. • Will continue to need rotating shift crew for tests • Still need to understand connection sequence and test procedure – MUCH more delicate if we have to test double harness, just from PP1 end. • Acceptance test (do we do it?) – 100 shifts • Tests after installation (if double harness) – 200 shifts • Tests of cables from PS to dPP1 after connection at PP3 – 300 shifts Pippa Wells

  5. Power supplies • Assume Jan Bohm, Jan Stastny and colleagues will provide staff, as before. • No additional shifts needed to test power supplies • Will also need detailed checks of mapping. DPP1 are supposed to have an LED incorporated, so visual checks of what switches on can be made. This might use the ad-hoc shifters as assistants.DCS/PS system tests – 100 shifts Pippa Wells

  6. DAQ/ROS, fibres • John Hill listed the UK people available for installation and testing • Fibre testing can not be done by ad-hoc shifters – will need a few trained people (probably also from UK) Pippa Wells

  7. DCS • See Pamela’s talk • Testing to be done by Richard Brenner, Pamela, Heidi… • Assume they need one ad-hoc shifter to assist – an additional (3hour, 1person) 30 shifts Pippa Wells

  8. Cooling, heaters, HEX • See Steve McMahon’s talk. • Relying on the ad-hoc shifters for cable testing during installation. Total of 700 cables. • Pixel institutes should also contribute here • 100 testing shifts Pippa Wells

  9. Tally of testing shifts needed • These are 3 hour, 1 person shifts. Usually they work in teams of two people, or assist an expert. • They must have access to the pit – training course to level 3, hard hat, safety shoes • Shift list totals don’t take into account the uneven load on institutes for more expert installation tasks Pippa Wells

More Related