North Texas Municipal Water District’s Proposed Lower Bois d’Arc Creek Reservoir

North Texas Municipal Water District’s Proposed Lower Bois d’Arc Creek Reservoir. Presented by: Jim Parks. Major North Texas Water Providers. NTMWD Treated Water Service Area. 13 Member Cities Allen Farmersville Forney Frisco Garland McKinney Mesquite Richardson Plano Princeton

arin
Télécharger la présentation

North Texas Municipal Water District’s Proposed Lower Bois d’Arc Creek Reservoir

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. North Texas Municipal Water District’sProposed Lower Bois d’Arc Creek Reservoir Presented by: Jim Parks

  2. Major North Texas Water Providers

  3. NTMWD Treated Water Service Area • 13 Member Cities • Allen • Farmersville • Forney • Frisco • Garland • McKinney • Mesquite • Richardson • Plano • Princeton • Rockwall • Royse City • Wylie • 49 Customer Cities, Towns & Water Supply Corporations

  4. NTMWD Raw Water Supply Sources

  5. 2007 State Water Plan for NTMWD

  6. Lower Bois d’Arc Creek Reservoir Fannin County, TX Area: 16,526 acres Storage: 367,609 ac-ft Supply: 113 MGD Average Depth: 22 ft Maximum Depth: 70 ft Lake Elevation: 534 ft msl

  7. Water Right Application • Submitted - December 2006 • Administratively complete - June 2007 • Interbasin transfer meetings -September 2007 • Supplemental application: • 401 & 404 applications • Outstanding Requests for Information: • Instream Flow Study • Reservoir Operating Plan • Downstream Impacts • Mitigation Plan

  8. 404 Permit Application • Submitted to USACE – June 2008 • EIS Determination – March 2009 • EIS Contractor Selected August 2009 • Public & Agency Scoping Meetings – December 2009

  9. 404 Permit Application • Required by USACE: • Jurisdictional Determination Report  • Habitat Evaluation Study – Reservoir Site  • Geomorphic Assessment of Streams  • Environmental Report  • Archeological Report – (begin spring 2010)

  10. Land Acquisition • NTMWD Board approved - November 2007 • Reservoir Site Land needed – 22,590 acres • Acquisitions to date - 9,991 acres (44%) • Riverby Ranch Mitigation Area • 14,958 acres

  11. Riverby Ranch Mitigation Area • 14,958 acres • Potentially meets all mitigation needs: • Created wetlands • Stream restoration • Uplands • Very unique opportunity

  12. Riverby Ranch Mitigation Area • Developing partnership with USFS to manage site • Double USFS lands within the region • USFS staff has shown strong support • Designated themselves as a “cooperating agency”

  13. Lower Bois d’ Arc ReservoirSchedule