1 / 6

Dr. V M Patel (Principal) Shankersinh Vaghela Bapu Institute Of Technology B.E. (Civil), M.E. (Structure – Gold Medal),

Points To Be Discussed During Visit Of Project Site. Presented By. Dr. V M Patel (Principal) Shankersinh Vaghela Bapu Institute Of Technology B.E. (Civil), M.E. (Structure – Gold Medal), Ph.D. ISTE, GICEA, ISES, AMIE, IGS(A ), FIV. POINTS TO BE DISCUSSED DURING VISIT OF PROJECT SITE.

bailey
Télécharger la présentation

Dr. V M Patel (Principal) Shankersinh Vaghela Bapu Institute Of Technology B.E. (Civil), M.E. (Structure – Gold Medal),

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Points To Be Discussed During Visit Of Project Site Presented By Dr. V M Patel (Principal) Shankersinh Vaghela Bapu Institute Of Technology B.E. (Civil), M.E. (Structure – Gold Medal), Ph.D. ISTE, GICEA, ISES, AMIE, IGS(A), FIV

  2. POINTS TO BE DISCUSSED DURING VISIT OF PROJECT SITE Client information (private, govt., semi govt., board, Panchayat, etc.) Time duration of project Estimated project cost Name of contractor / builder / developer Name of architect / structural / drainage / plumbing / electrical / air conditioning / horticulture / interior / PMC consultant Type of tender / contractor work contract

  3. POINTS TO BE DISCUSSED … Any Bar Chart or other method adopted for progress monitoring Any problem they faced during the planning & solution of it Any problem they faced during the execution & solution of it Development length, anchorage, splicing of bar proper or not Construction joint, member joint and separation joint Any special care or treatment adopted on site Any innovative idea implemented for increasing strength or decreasing cost or time

  4. POINTS TO BE DISCUSSED … Construction cost per sq. mtrs. Floor area FSI, carpet area and built up area calculation Land rate at the time purchase of land and at the time of project completion Safety of labour and engineers on site High tech. equipments used for the project execution Design and execution quality check / monitoring authority while showing deficiency)

  5. POINTS TO BE DISCUSSED … Take photographs as many as possible with permission Do not misuse the data of project site (do not mention project name while showing deficiency) Prepare site visit report with all mentioned details.

  6. Thank You For Your Kind Attention! Dr. V M Patel, Principal, SVBIT, Gandhinagar