1 / 16

SPD-cooling status

SPD-cooling status. Rosario Turrisi INFN Padova. Foreword: working principle. Evaporative system Joule-Thomson cycle: sudden expansion + evaporation at constant enthalpy Fluid: C 4 F 10 Dielectric Chemically stable Non-toxic. liquid pressure ≡ flow gas pressure ≡ temperature.

bedwell
Télécharger la présentation

SPD-cooling status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SPD-cooling status Rosario Turrisi INFN Padova

  2. Foreword: working principle • Evaporative system • Joule-Thomson cycle: sudden expansion + evaporation at constant enthalpy • Fluid: C4F10 • Dielectric • Chemically stable • Non-toxic liquid pressure ≡ flow gas pressure ≡ temperature

  3. Simplified schema Detector side • 2 filters (60 μm) before SPD, in PP4, PP3 • Read-out of p,T per line up- (PP4) and downstream (PP1) the detector • Detector side not accessible, except PP4, PP1 Plant side

  4. Actions taken • Additional heat exchangers to further subcool the fluid close to the detector • 10 HX’s (one per line), redundant exchange factor (more than 5 times) • use leakless system with water cooled down at 7.5 °C • Installation of new liquid-side pipes • dedicated path of new lines, more straight (less elbows), shorter • inox SS316L, 6/4 o/i diameter (same as before) - no insulation (useless) • Flushing each line counter-flow wise • drain particles clogging the filters outside the line • redundant protection against overpressure: 2 safety valves (mechanical) + pressure switch (electronic) • 2 filters, stainless steel, 1 μm grid, on the “washing machine” • 24 h washing cycle per each sector

  5. Room for improvement? From LHCC meeting November 16 • Out of 10 “missing” 9 half-staves have cooling issues • Beyond the number of hs, SPD needs also stability • Following actions need to be taken on solid base, understanding the behaviour in running conditions (lots of variables play...) • Actions for the short term: • remote control of water flow • installation of per-line flowmeters and pressure regulators • repeat the cleaning on worse sectors (7,9) for longer time notneeded The real schedule is of course dependent on when/how long we’ll have access to the experimental area...

  6. ‘Ice age’ test #2 • We wanted to verify if subcooling the freon can help the performance on “critical” sectors (#7 & #9) • We installed in PP4 (close to SPD) ~8 m of plastic pipe in a bucket filled with snow • freon reached ~8 °C in PP4 • Test done on the two worst sectors (#7 and #9) • No significant change of the performance observed Valuesof the bus current for the 6hsof side A - missingmeans off

  7. Measurement of flow flow [g/s] • We measured the flow on a few sectors with a single flowmeter (on a common line) • Better understanding of the performance can be achieved measuring the flow (and then the impedance) by a non evaporating fluid (we’ll use C6F14) • Special care to be taken, the non-evaporative flow prevents control of the pressure inside the detector but by regulating the input • Will be done as soon as we can have a reliable readout of flow and the cleaning of the “bad” sectors is done (use the same device) good p [bar] bad

  8. New hardware - 1 • Pressure regulator on each line: • allows a dedicated tuning of liquid pressure → flow • Flowmeter on each line: • allows the monitor of the flow → fundamental for performance monitoring along the lifetime of the system and debugging of possible problems • Hardware installation completed (sensors + cabling) • Readout system close to completion (next week), integrated in DCS

  9. New hardware -2 • Pressure regulators: Swagelok KPR series, stainless steel with dedicated “peek” gaskets • Flowmeters: Bronkhorst ‘Mini Cori Flow’: • very expensive but necessary to handle the low flows of SPD • based on Coriolis-forces effects, no needles/balls/whatever in the fluid path

  10. A few pictures...

  11. Planning to week 4 Commissioningdelayedto week 4 (25th-29th Jan) toallowlongercleaningofsectors #7 and #9 today

  12. Critical tasks to week 4 today Commissioningdelayedto week 4 (25th-29th Jan) toallowlongercleaningofsectors #7 and #9

  13. Summary • Hardware upgrade of the system completed • A few maintenance interventions to go • Cleaning of the worst lines ongoing (sects. #7 & #9) • By the end of January: • measurement of the flow with non-evaporating fluid • commissioning

More Related