This report summarizes the current testing status of the 20 ACORDE modules, electronic cards, and cables, all of which have been tested prior to installation. The testing of the top and bottom structures occurred inside a controlled clean room. The 10 ACORDE modules located on top have successfully passed their tests. Additionally, the user interface for ACORDE has been completed. The final tests for the top and bottom modules are scheduled for next week, with readiness for the TPC test anticipated by May 1st.
E N D
Status • All the 20 ACORDE modules, electronics cards and cables have been tested before the instalation on the structure. • The top and bottom structures are inside the clean room. • The 10 ACORDE modules on top have been tested inside the clean room. • The ACORDE user interface has been finished. • The last test with the top and bottom modules will be made next week. • ACORDE will be ready for the TPC test on the 1st May.