40 likes | 129 Vues
This report provides a detailed overview of the recent events and quotations related to the common crate project FV. It includes pricing information for bins, backplanes, fan-trays, and power supplies, as well as details on orders placed and delivery expectations. The project involves multiple components such as LAV FE, LKr trigger, and backplane design, with charges shared among future TEL62 buyers. The crates are scheduled for delivery in April and all components can be ordered through the PH-ESE technical database. Stay informed on the latest developments in this essential project.
E N D
Events happened after the December meeting • Quotations' story • 22.12.10 • Bin (9ULHC version 2, 11U high, 21 positions 9U, 400mm in depth, withoutbackplane, fan-tray 400mm - 2'075. EUR/pc • Backplane 3U according to NA62 specification, minimum quantity 20 units - 696. EUR/pc • Fan-tray 9U 400mm in depth - 627.-EUR/pc • Power supply LHC 6U, +/-12V 46A, 48V 13.5A, +3.3V 30A, +5V 30A /-5V 30A - 3’871 EUR/pc • Power supply LHC 9U, 48V 27A, +3.3V 100A, +5V 100A, +/-5V 100A - 3’295.EUR/pc • 13.01.11 • Bin - 2'075. EUR/pc • Backplane – 1 unit - 1’256. EUR/pc • Backplane design and tooling – 3240 EUR/pc • Fan-tray - 627.- EUR/pc • Power supply LHC 9U, +/-12V 46A, 48V 13.5A, +3.3V 100A, +5V 100A,+/-5V 30A - 3’738 (3’871 ) EUR/pc • Power supply LHC 9U, 48V 27A, +3.3V 100A, +5V 100A, +/-5V 100A - 3’295. EUR/pc VF
Quotations' story - 2 • 14.01.11 • Bin - 2'075. EUR/pc • Backplane – 2 units - 988. (1’256.) EUR/pc>=20 units - 534. EUR/pc • Backplane design and tooling – 3240 EUR/pc • Fan-tray - 627.- EUR/pc • Power supply LHC 9U, +/-12V 46A, 48V 13.5A, +3.3V 100A, +5V 100A ,+/-5V 30A - 3’738 EUR/pc • Power supply LHC 9U, 48V 27A, +3.3V 100A, +5V 100A, +/-5V 100A - 3’295. EUR/pc VF
The order was sent on January 15 • 2 complete crates • LAV FE (Antonella) • LKr trigger (Andrea) • Backplane design and tooling (Ferdi – common fund). This charges will be sheared among the future TEL62 buyers. • Design of the backplane will be agreed with the NA62 • The crates should be delivered in April • All crate components are included in the PH-ESE technical database and can be ordered directly through it any time VF