1 / 21

Examining the project

This chapter explores gathering and analyzing information to make decisions about project progress, including what has happened, what is happening, what should have happened, and what should be happening.

carmelinak
Télécharger la présentation

Examining the project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Examining the project

  2. What is this chapter about? • Gathering and analysing information for decision making in (and about) running projects: • What has happened • What is happening • What should have happened • What should be happening • Process of gathering information: monitoring & controlling

  3. Processes can be… • Time related • Cost related • Or related to both

  4. Time related processes • Concerned with the activities in the project plan: • Determination of logical interactions • Estimation of durations • Schedules and key event schedules(with identification of critical activities) • Focus of control is on the future. If not, it will degenerates into a recording system • Consistent unit of time throughout the plan (with the exemption of different levels of detail).

  5. Cost related processes • Goal: to complete the project within the financial budget, including forecasting and managing costs. • Estimation of activity costs for the budget-plan are based on: • Labor-hours (man-hours) • Labor-rates (wage etc.) • Material costs • Service costs • Set-up charges • Rental charges • Overheads • Cost control is based on the budget • Cost control is the principal means of control (esp. for the customer)

  6. Resource related processes • Aim: to plan the use and control of resources. • Resources: anything (any input) that is required. Availability of resources means constraints for the project. • Resource planning: • Summation (aggregation) for each period • Scheduling activities with resource needs • Coming only after the scheduling of activities by logical interactions • Resource control: monitor the usage of resources and report any deviations to the plan

  7. Planning project duration Network techniques: a formal and explicit statement of policy, and also a communication tool • Statement of Work (SoW) • Work Breakdown Structure (WBS) • Logical sequencing of the project • More thanonelogic can be appropriate(depending on the project-context): • Physical • Functional • Cost-centre etc. • Assign the durations to the tasks and task groupsUse iterative refining of the duration estimations • Examination of the plan: ‘there is always a better way’Project network techniques identifies the critical activities to focus the examinations on. Duration reduction always costs resources.

  8. Reducing total project time (TPT) Systematic approach: • Critical activities subjected to the questioning technique (if there is a quicker way) • Can we modify the network logic to overlap or parallel activities? • Is it acceptably possible to increase the risk taken? • Can any resources moved or can the costs of increased resources be tolerated?

  9. The questioning method • Its backround is work-study • Systematic questioning: the same questions on the same (rigid) way • Two kinds of activities: • ‘do’ activities: tasks advancing the project in themselves • ‘ancillary’ activities: supporting ‘do’ activities

  10. Questions to be asked when reducing the project time ? • Purpose • Place • Sequence • Person • Means • Overlapping • Risk • Trade-off • Cost

  11. Reduction by overlapping activities Activities following each other, depending on the interrelationships can be overlapped or paralleled. actvity name 1st day 2nd day 3rd day 4th day 5th day actvity ‘A’ actvity ‘A’ Original sequence actvity ‘B’ actvity ‘B’ actvity ‘A’ actvity ‘A’ Overlapping activities actvity ‘B’ actvity ‘B’ actvity ‘A’ actvity ‘A’ Parallel activities actvity ‘B’ actvity ‘B’

  12. Reduction by increased risk • Reducing (sub-)activities like: • Testing • Checking • Proving • Risk of failure will increase

  13. Reduction of time by the transference of resources • Trading-off resources: moving resources from non-critical activities to critical ones (to speed them up).

  14. Reduction of time by increased cost („cost slope concept” or „crashing”) • Increasing activity cost to reduce its duration. • Cost-slope: cost of reducing duration time by unit time. • We need network diagrams to do crashing.

  15. Dangers of the 'cost-slope concept' • It is difficult to find reliable figures for the changes in cost resulting from changes in duration times. • Cost/time relations are frequently neither constant nor simple • Not all resources are freely convertible to cost (problem of availability)

  16. Reducing cost by increasing time • Non-critical activities can be increased in time without extending the duration of the whole project (they have float time). In this case cost savings are the only effect.

  17. Relationship between time and labour employed There is a minimum time below it is impossible to reduce duration.

  18. The final network • The network after reduction will be different than the one before: • Logic and connections changed between activities • Duration times altered • New critical path or paths • A test is needed to uncover illogicalities and to match the new activity schedule to the resource availabilities

  19. Reading • Textbook chapter 8

  20. Thank you for listening

More Related