VENKATANAGARAM PUMPING SCHEME

VENKATANAGARAM PUMPING SCHEME. LOCATION OF THE PROJECT. At Km 12.34 of Akhanda Godavari Left Bank Longitude 81°- 35’ – 56” E Latitude 17°- 8’ – 30” N Near Katheru village 5 km from Rajahmundry. SALIENT FEATURES. Water proposed to be lifted - 9.90 cumecs.

chars
Télécharger la présentation

VENKATANAGARAM PUMPING SCHEME

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. VENKATANAGARAM PUMPING SCHEME

  2. LOCATION OF THE PROJECT • At Km 12.34 of Akhanda Godavari Left Bank • Longitude 81°- 35’ – 56” E • Latitude 17°- 8’ – 30” N • Near Katheru village • 5 km from Rajahmundry

  3. SALIENT FEATURES • Water proposed to be lifted - 9.90 cumecs. • Ayacut proposed to be irrigated - 36,000 Acs. • Drinking water facilities to 1,20,000 population in 28 villages.

  4. ADMINISTRATIVE APPROVAL • Administrative approval was accorded vide G.O.Ms.No.135, dt.7-8-2005 • Sanctioned estimate no.& amount CR.No.49/2004-05, dt.3-1-2005, Rs.97,07,38,000 • Work entrusted to M/s.Koya & Co.Construction Pvt. Ltd.,Hyderabad. • Agreement No.& Value 67/2004-05, dt.14-3-2005 Rs.85,56,59,700

  5. PROJECT COMPONENTS • Stage I:- Lifting of water from River Godavari at KM 12.34 of Akhanda Godavari Left Bank from +12.00 to +19.00. Ayacut benefitted 2,000 Acs existing ayacut. • Stage II (a):- Lifting of water from +18.50 to +26.50m. Ayacut benefitted 2,250 Acs existing ayacut. • Stage II (b):- Lifting of water from + 18.50 to +88.20m Ayacut benefitted 25,750 Acs new ayacut. • Stage III (From stage II main canal):- Lifting of water from +85.00 to +110.80m Ayacut benefitted 6,000 Acs

  6. LAND ACQUISITION • Land to be acquired for Head works, pressure main 69 Acs. • Land to be acquired for Distributory system 153 Acs.

  7. BENEFITS • On completion of the pumping scheme 21,408.30 MT of food grains valued at 62.88 crores will be produced annually. • Drinking water facility for a population of 1,20,000 people living in 28 villages. • B.C. ratio 3.38:1

  8. POWER & WATER REQUIREMENT Water Requirement: 3.62 TMC Power Requirement: 10 MW

  9. BUDGET & EXPENDITURE • M.H.161 Venkatanagaram Pumping Scheme • 530 Major works Budget Expen. (Rs. in Lakhs) • 531 Other Expenditure 7,000 4,27-83 • 532 Lands 100 --