This document provides an overview of the progress for various projects under the Facilities Modernization Program at Las Positas College as of March 19, 2012. It includes updates on multiple phases like the Outside Loop Road, Science Building Phase II, Student Services & Central Administration, Campus Boulevard Phase I-III, and Photovoltaic System Phase II. Key teams and contractors involved are listed, along with current project statuses, occupancy timelines, and major construction updates for each initiative.
E N D
Facilities Modernization Program Funded by Measure B Project Report March 19, 2012
PROJECT PROGRESS REPORT PE Phase III (Outside Loop Road) LAS POSITAS COLLEGE March 19, 2012 • Project Team: • Architect: WLC Architects / Carducci Landscape Architects • Construction Manager: Parsons Brinckerhoff • Contractor: Lathrop Construction Project Update: • Project is complete. • DSA Closeout is in progress. • Occupancy: 04/2011
PROJECT PROGRESS REPORT Science Building, Phase II LAS POSITAS COLLEGE March 19, 2012 • Project Team: • Architect: Kwan Hemni • Construction Manager: Parsons Brinckerhoff • Contractor: Broward Builders, Inc • Project Update: • Interior Casework, Lighting and Fume hoods being installed. • Exterior Painting is in progress. Interior Painting is Completed. • Electrical and Data installation and termination is continuing at first and second floors. • Flooring at 2nd floor classrooms completed. • Storefront installation and Glazing Completed. • Stair Treads installed. Occupancy: 09/2012
PROJECT PROGRESS REPORT Student Services & Central Administration LAS POSITAS COLLEGE March 19, 2012 • Project Team: • Architect: Steinberg Architects • Construction Manager: Parsons Brinckerhoff • Contractor: Zovich Construction • Project Update: • GFRC installation complete. • Storefront installation has started along with glazing. • Site fine grading is complete. • Building metal panels have to start within 2 weeks. • Sheetrock has started on one side of the walls. • Elevator installation to begin next week. • Roofing is complete. Occupancy: Spring 2013
PROJECT PROGRESS REPORT Campus Boulevard Phase I-III LAS POSITAS COLLEGE March 19, 2012 • Project Team: • Architect: Gates & Associates • Construction Manager: Parsons Brinckerhoff • Contractor: TBD Project Update: • 100% Design review completed, final design was Approved by DSA February 2012. • Project was Bid on March 13, 2012 and Low Bid Contractor will be Board Approved April 17, 2012 • Design Re-Start: 04/2011 • DSA Permit Approval: 02/2012 • Construction Start: 05/2012 Occupancy: TBD
PROJECT PROGRESS REPORT Photovoltaic System Phase II LAS POSITAS COLLEGE March 19, 2012 • Project Team: • Design Build Contractor: Cupertino Electric Inc. • Construction Manager: Parsons Brinckerhoff Project Update: • Fencing Completed. • Racking System and Array installation is completed. • Inverters and Transformer installed and completed. • New Switchgear tie in during Spring Break. Operational: February 2012