This report outlines the progress of multiple modernization projects at Las Positas College as of October 15, 2012. Key updates include the completion of ceiling tile installations on the second floor, ongoing flooring work, and the nearing completion of elevator and site concrete works. The Campus Boulevard project has achieved significant milestones, with pathways and utilities almost complete. Additionally, the Science Building Phase II is nearing completion, with ongoing punch list work. Occupancy for various projects is scheduled between Fall and Spring 2013.
E N D
Facilities Modernization Program Funded by Measure B Project Report October 15, 2012
PROJECT PROGRESS REPORT Student Services & Central Administration LAS POSITAS COLLEGE October 15, 2012 • Project Team: • Architect: Steinberg Architects • Construction Manager: Parsons Brinckerhoff • Contractor: Zovich Construction • Project Update: • Ceiling tile is being installed on the 2nd floor. 85% complete. • Carpet/Sheet Vinyl to start installation on 2nd floor this week. Tile installation in the 1st floor kitchen area has started. • All tile in bathrooms complete along with fixture installation. Testing of plumbing fixtures has started. • Elevators installation is 90% complete. • Site concrete is 85% complete. Irrigation is complete and planting is underway. Occupancy: Spring 2013
PROJECT PROGRESS REPORT Campus Boulevard Phase I-III LAS POSITAS COLLEGE October 15, 2012 • Project Team: • Architect: Gates & Associates • Construction Manager: Parsons Brinckerhoff • Contractor: Suarez & Munoz Construction, Inc. Project Update: • Concrete Pathways 95%Complete, with the Library and Grand Stairs 98% Complete • Underground Electrical and Lighting are 100% Complete • Boulders for the wet fountain have been placed, with the dry fountain to be placed weekend of 9/20/12 • Underground Utilities, mainlines and laterals are 90% completed. • Grading work has started with plants arriving week of 9/16/12 • Occupancy: 11/02/12
PROJECT PROGRESS REPORT Science Building, Phase II LAS POSITAS COLLEGE October 15, 2012 • Project Team: • Architect: Kwan Hemni • Construction Manager: Parsons Brinckerhoff • Contractor: Broward Builders, Inc • Project Update: • New Science Bldg 1850 Complete, Punch List work in progress • Bldg 1800 Remodel Complete, Punch List work in progress • Closeout in progress Occupancy: 09/2012