1 / 4

Facilities Modernization Program Funded by Measure B Project Report

Facilities Modernization Program Funded by Measure B Project Report. October 15, 2012. PROJECT PROGRESS REPORT Student Services & Central Administration. LAS POSITAS COLLEGE October 15, 2012. Project Team: Architect : Steinberg Architects Construction Manager : Parsons Brinckerhoff

tallis
Télécharger la présentation

Facilities Modernization Program Funded by Measure B Project Report

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Facilities Modernization Program Funded by Measure B Project Report October 15, 2012

  2. PROJECT PROGRESS REPORT Student Services & Central Administration LAS POSITAS COLLEGE October 15, 2012 • Project Team: • Architect: Steinberg Architects • Construction Manager: Parsons Brinckerhoff • Contractor: Zovich Construction • Project Update: • Ceiling tile is being installed on the 2nd floor. 85% complete. • Carpet/Sheet Vinyl to start installation on 2nd floor this week. Tile installation in the 1st floor kitchen area has started. • All tile in bathrooms complete along with fixture installation. Testing of plumbing fixtures has started. • Elevators installation is 90% complete. • Site concrete is 85% complete. Irrigation is complete and planting is underway. Occupancy: Spring 2013

  3. PROJECT PROGRESS REPORT Campus Boulevard Phase I-III LAS POSITAS COLLEGE October 15, 2012 • Project Team: • Architect: Gates & Associates • Construction Manager: Parsons Brinckerhoff • Contractor: Suarez & Munoz Construction, Inc. Project Update: • Concrete Pathways 95%Complete, with the Library and Grand Stairs 98% Complete • Underground Electrical and Lighting are 100% Complete • Boulders for the wet fountain have been placed, with the dry fountain to be placed weekend of 9/20/12 • Underground Utilities, mainlines and laterals are 90% completed. • Grading work has started with plants arriving week of 9/16/12 • Occupancy: 11/02/12

  4. PROJECT PROGRESS REPORT Science Building, Phase II LAS POSITAS COLLEGE October 15, 2012 • Project Team: • Architect: Kwan Hemni • Construction Manager: Parsons Brinckerhoff • Contractor: Broward Builders, Inc • Project Update: • New Science Bldg 1850 Complete, Punch List work in progress • Bldg 1800 Remodel Complete, Punch List work in progress • Closeout in progress Occupancy: 09/2012

More Related