1 / 8

Facilities Modernization Program Funded by Measure B Project Report

Facilities Modernization Program Funded by Measure B Project Report. April 19, 2010. PROJECT PROGRESS REPORT College Center for the Arts. LAS POSITAS COLLEGE April 19, 2010. Project Team: Architect : John Sergio Fisher & Associates Construction Manager : Parsons Brinckerhoff

frisco
Télécharger la présentation

Facilities Modernization Program Funded by Measure B Project Report

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Facilities Modernization Program Funded by Measure B Project Report April 19, 2010

  2. PROJECT PROGRESS REPORT College Center for the Arts LAS POSITAS COLLEGE April 19, 2010 • Project Team: • Architect: John Sergio Fisher & Associates • Construction Manager: Parsons Brinckerhoff • Contractor: C. Overaa & Co Project Update: • The exterior siding, stucco and windows are 99% complete. • The interior of the building is 97% complete in segment "B" which is the facility offices and the rehearsal rooms. • The Black Box Theater and the Main Auditorium infrastructure elements are continuing and will be completed this • month. • The final concrete walk ways and ramp around the building and the Amphitheater are 98% complete. • The total project is 95% complete. • Occupancy Fall Semester 2010

  3. PROJECT PROGRESS REPORT Child Development Center LAS POSITAS COLLEGE April 19, 2010 • Project Team: • Architect: Beverly Prior Architects • Construction Manager: Parsons Brinckerhoff • Contractor: Lathrop Construction Associates Project Update: • Exterior plaster complete on all buildings. • Installation of sheetrock continues in building B and has started in building C. • Rough grading for the OLEs has begun. Occupancy Spring 2011

  4. PROJECT PROGRESS REPORT PE Phase III (Outside Loop Road) LAS POSITAS COLLEGE April 19, 2010 • Project Team: • Architect: WLC Architects / Carducci Landscape Architects • Construction Manager: Parsons Brinckerhoff • Contractor: Lathrop Construction Project Update: • Underground & electrical utilities are continuing. Occupancy: 10/2010

  5. LAS POSITAS COLLEGE April 19, 2010 PROJECT PROGRESS REPORT Collier Creek Storm Water Outfall • Project Team: • Engineer of Record: Sandis • Construction Manager: Parsons Brinckerhoff • Contractor: Lathrop Construction Project Update: • Storm Drain and Retaining wall installation is complete. • Backfill at retaining wall is on going. • Occupancy: 04/2010

  6. PROJECT PROGRESS REPORT Science Building, Phase II LAS POSITAS COLLEGE April 19, 2010 • Project Team: • Architect: Kwan Hemni • Construction Manager: Parsons Brinckerhoff • Contractor: TBD • Project Update: • Added space for 4 classrooms on second floor. • Site layout and floor plan finalized. • Projected submittal to DSA in March 2010. Occupancy: Fall 2012

  7. PROJECT PROGRESS REPORT Student Services & Central Administration LAS POSITAS COLLEGE April 19, 2010 • Project Team: • Architect: Steinberg Architects • Construction Manager: Parsons Brinckerhoff • Contractor: TBD • Project Update: • 60% design documents were submitted in April • DSA submittal planned for August 2010, • This project will participate in the new DSA Collaborative Process. Occupancy: Fall 2012

  8. PROJECT PROGRESS REPORT Campus Boulevard Phase I-III LAS POSITAS COLLEGE April 19, 2010 • Project Team: • Architect: RHAA • Construction Manager: Parsons Brinckerhoff • Contractor: TBD Project Update: • Design stopped to coordinate with SSA design concepts. Occupancy: Fall 2011

More Related