Lagos BRT Lite Success Story A Presentation at the: 2009 Sub-Saharan Africa Transport Policy(SSATP) Annual Meeting

Lagos BRT Lite Success Story A Presentation at the: 2009 Sub-Saharan Africa Transport Policy(SSATP) Annual Meeting. By Dr Dayo Mobereola MD/CEO Lagos Metropolitan Area Transport Authority (LAMATA). Planning for17 million inhabitants

corby
Télécharger la présentation

Lagos BRT Lite Success Story A Presentation at the: 2009 Sub-Saharan Africa Transport Policy(SSATP) Annual Meeting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Lagos BRT Lite Success Story A Presentation at the:2009 Sub-Saharan Africa Transport Policy(SSATP) Annual Meeting By Dr Dayo Mobereola MD/CEO Lagos Metropolitan Area Transport Authority (LAMATA)

  2. Planning for17 million inhabitants Smallest state in Nigeria with total area of 357,700 Hectares. Most populous city in Africa. Current estimated growth rate is 6%, hence by 2020, population is expected to be 35 million. Hub of nation’s economic, commercial and industrial activities. 45% of nation’s skilled manpower reside in the city. Houses the nation’s principal commercial sea and airports. BACKGROUND

  3. Overview of transport problems in Lagos State The most evident symptoms are the notorious traffic jams

  4. What public transport used to be in Lagos Rail Danfo Rail Corridor Okada Disused Ferry

  5. THE PLANNING OF BRT

  6. BRT Planning • Lagos Urban Transport Project (LUTP) • Creation of strategic transport authority –LAMATA • ITP feasibility study, surveys and preliminary design • Lagos State Government approval • Public sector infrastructure provision and maintenance • Private sector finance – ECO Bank

  7. BRT Planning cont. • Early engagement of transport unions and study visit - Creation of BRT Co-op • Bogota • Curitiba • Sao Paulo • Stakeholder meetings/formation of operating consortium • Series of meetings to explain the concept of BRT

  8. BRT Corridor

  9. PPP FRAMEWORK FOR DELIVERING BRT

  10. Segregation Barriers (60% of the Corridor) Bus Shelters and Lay Byes (26 stops @ 500 – 1000m) 3 Terminals Bus Depot/Garage Service Lane Repairs Lighting Fencing Traffic Signs and Road Markings 22 km lane overlay 3.3 m wide BRT lane INFRASTRUCTURE PROVIDED BY LAMATA

  11. BRT Infrastructure BRT Terminal at CMS Segregation Bus Depot at Ketu/Ojota

  12. BRT Signage/Lane Marking

  13. Terminal at Mile 12/Moshalashi

  14. PPP FRAMEWORK FOR BRT IMPLEMENTATION CONT. PRIVATE SECTOR PROVIDES THE FOLLOWINGS: • Acquisition of buses • Recruiting and training of personnel • Manages operations

  15. BRT OPERATIONS

  16. BRT Operations • BRT Lite was successfully launched in March 2008 • 220 buses in operations • Hours of operations- 6:00am – 10:00pm • Headway– Max 10mins

  17. BRT Operations Contd. • Over 900 bus pilots and bus officers • LASTMA’s role – Traffic Management, Breakdowns and Enforcement • 57 inspectors • Fares – 2 zone system • Security outsourced • Monitoring team • Compliance officers

  18. BRT Performance • Daily ridership exceed 200,000 • Average Load factor of 1000 passengers carried per bus per day • Average trip per day is 5 • Average waiting time of 15mins • Average speed of 45km/h • Average journey time of 55mins • Over 86 million ridership since inception • Fleet capacity utilization is 95% • Fuel consumption per bus per day is 80 liters • Average passenger kilometer per day is 5 • Kilometers per bus per day is 220

  19. VOLUME OF RIDERSHIP SINCE INCEPTION

  20. Achievement of Lagos BRT • Reform within the existing operators • Financial institution involvement in PT • Capacity building and trust in LAMATA • BRT has so far recorded higher patronage than expected • Improved mobility along Mile 12/Moshalahi-CMS corridor • Ordered boarding

  21. Achievement of Lagos BRT • Reduction of travel time by 29% • Significant drop in pollutants since inception • 33% decrease in transport fare • Improved transit connections

  22. NEXT STEPS • Extension and expansion of BRT network • Integration with planned water/rail systems • Migration to electronic ticketing • Continued training of operations personnel and pilots • Introduction of formal feeder routes and Park Ride

  23. FINANCIAL MODEL

  24. FINANCING • Ecobank provided BG for 100 buses through deferred payment with the sum of N48 million required to be set aside as loan repayment to the bank • Ecobank appointed 12 ticket dealers • Tickets are domiciled with Ecobank • Ticket dealers buy tickets directly from Ecobank for revenue security • Ecobank provided a cash flow projection • Tickets are colour coded for ease of identification • 2 fare zones – N50 and N100

  25. FINANCING CONT. • The state Government leased 120 buses to the NURTW Coop. • A total of N36,000,000 is paid monthly