1 / 20

Experimental Areas – Hardware Tests for 2006 startup

Experimental Areas – Hardware Tests for 2006 startup. Outline SPS North Area Changes since 2004 Commissioning plan / HW tests Where do we stand Future steps – critical items PS East Area AD Experimental hall. Ilias Efthymiopoulos – AB/ATB/EA. PS-SPS Days - 2006 CERN – January 18, 2006.

donclark
Télécharger la présentation

Experimental Areas – Hardware Tests for 2006 startup

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Experimental Areas – Hardware Tests for 2006 startup Outline SPS North Area Changes since 2004 Commissioning plan / HW tests Where do we stand Future steps – critical items PS East Area AD Experimental hall Ilias Efthymiopoulos – AB/ATB/EA PS-SPS Days - 2006 CERN – January 18, 2006

  2. Changes since 2004 (1/7) SPS North Area Beam Lines • Three experimental halls : EHN1, EHN2 (COMPASS), ECN3 (NA48) • 7 beam lines ; ~1000 equipment installed ; total length > 6 Km • ~1500 users performing experiments and tests ; frequent changes of beam configuration and settings Total no. of requests keeps increasing 30 experiments & tests in 2006 • 80% to be installed in EHN1; the rest in PS East Hall • West Area was dismantled in 2005 • More frequent user changes and beam settings ; sharing of beam time

  3. Changes since 2004 (2/7) EA Renovation Project (SPS Beam Lines) Started 5 years ago, arrives to completion in 2006 Highlights of the project: Hardware renovation • BDI hardware from CAMAC to VME equipment oriented modules • Introduce new hardware (PLCs) to replace custom solutions and promote standardization (i.e. vacuum to AT/VAC standard PLCs) • Migrate the magnet control from the “junction crate” (G64) to VME • Replace obsolete NCD X-terms in BDI and user barracks by PC’s • Upgrades to the access system and timing distribution to new standards Software renovation • Introduce new control software “CESAR project” following the AB/CO standard solutions to replace NODAL • Allow improved user interface and facilities to help operations and maintenance • Use of FESA and PLC software for the front-ends

  4. Changes since 2004 (3/7) EA Renovation Project (SPS Beam Lines) Started 5 years ago, arrives to completion in 2006 For the SPS 2006 startup, all the North Area will be switched to the new system • Following successful tests in 2004 in the West Area and with selected users in the North Area (NA60) What is new: • New HW for the majority of the beam diagnostics instruments to VME modules • The remaining ones are foreseen for later in Summer ‘06 • The front-end software for a large number of equipment is switched to FESA • For the rest, the “gateway” of SL-Equip will be used • All vacuum pumps will be controlled by standard AT/VAC PLCs via PVSS

  5. Changes since 2004 (4/7) BDI hardware renovation: Before: function oriented approach  Now : equipment oriented approach 10 barracks full with electronics completely refurbished in 2005

  6. Changes since 2004 (5/7) …What is new : • The control software will be CESAR ; it includes: • New user GUIs • New databases for layout, parameters and settings files • Use of AB/CO “standard” products for alarms, logging, timing • Possible to run from Linux or Windows PCs • Jython as scripting language • Can be used for the development of expert tools • Link to access system via FESA and special gateway • No HW changes to the access system itself • New timing distribution using CTDV / TG8 • TG3 remains in use for the magnets – will be changed once upgraded to VME control

  7. Changes since 2004 (6/7) In addition: • New shielding in TCC2 for the EHN1 beam lines • To respect the new (lower) radiation limits and in view of the running at higher intensities for M2/COMPASS • Upgrade of M2 beam line to reduce background at the experiment • Possibility to run at higher (20%) intensities • New experimental areas and interlock chains • Required to accommodate the large number of users • Replace an old “manual” dump with a mobile remotely controlled one • Cabling renovation in TCC2

  8. Changes since 2004 (7/7) New shielding in TCC2 : Protect the EHN1 hall from muons produced at the T4,T6 targets Ideal storage of old radioactive blocks!!!

  9. Commissioning Plan (1/2) • Dry Run-1 (10 -11 November 2005)- test two beam lines {H2, H4} • Dry Run-2 (27 – 31 March 2006) – test the whole of the North Area • Dates to be confirmed this week – new dates to better fit work plan • Commissioning with Beam • During week 24 (12-15 June) with extracted beam into the areas • Dates must be fixed to inform users beforehand and prohibit access to the areas

  10. Commissioning Plan (2/2) Goals • Validate proper functioning of all equipments • Validate proper functioning of control system under full load • Was the main worry during the early tests in 2004 • Validate BDI diagnostic tools, required for HW commissioning • Expert tools under development within CESAR project and/or using the FESA equipment navigator • Simulate the commissioning, and operation of the beam lines • Test as much as possible without beam during the Dry Runs • Final test during the commissioning phase with beam • The easy and reliable way to identify cabling or software errors!!

  11. Where do we stand (1/6) Dry Run-1 : 10-11 November 2005 • Used the small “PCR” installed at the AB/CO Pavillion (bat. 936) • Usefulness of the exercise validated and appreciated by everybody • Tight deadline but a serious effort was put to meet that milestone • As an example, it allowed to identify early enough a “forgotten” piece of software • A working system was provided in both Windows & Linux • All available HW and software parts were integrated • About 15 people actively participated during the two days of the event from several AB groups: OP, CO, PO, BDI, ATB,… • Positive feedback was received for the CESAR GUIs and the implemented functionalities • Requests for improvements and corrections collected, most of them will be implemented for the Dry Run-2

  12. Where do we stand (2/6) CESAR GUI window:

  13. Where do we stand (3/6) … Dry Run-1 : 10-11 November 2005 • No slow-down in performance was observed • Tests made to simulate realistic load conditions • Good performance thanks to the move to FESA-2 and improvements inside CESAR On the negative side: • Handing of exceptions coming from CMW and Equipment must be improved • It was the origin of the only “freeze” of the system • The problem is now understood and fixed - will be tested again in Dry Run-2 • Due to the missing software part the test of the access system was not possible • Although the HW was available on time • One of the major tests for Dry Run-2

  14. Where do we stand (4/6) Dry Run-1 – Summary The basic components of the beam lines were successfully tested and work • Magnets, collimators, beam profile counters • Thanks to an effort put to recompile and restart NODAL on the latest Linux version which allowed to use the SL-Equip and Equip-bus software to run • BDI equipment on new hardware and FESA • Beam counters ; filament scanners ; particle counters • Upgraded equipment on PLC and FESA • In/Out motorized equipment • Vacuum control using AT/VAC PVSS standard and readout in CESAR • Control system functionalities • Beam file handling ; beam tuning programs (“scan”); element navigators; information display

  15. Where do we stand (5/6) Dry Run-2 : What will be tested • Originally foreseen for middle of February – moved to end of March to allow testing a larger number of components • We would like to do it from the newly inaugurated CCC !!! • The Access system {access doors, safety chains} • Including the LOKN logic which defines de basic safety conditions for the NA beams • The timing distribution – for Dry Run-1 some events were simulated • The remaining BDI renovated equipment • Particle Identification devices {calorimeter, Cherenkov counter, delay wire chambers} • Additional functionality in the CESAR control software • GUI for scrapers, fixed collimators, SEM readout and target control • Protocol to send data and information to the experiments • Login and security mechanism for the users • Jython interface for online scripting language • First test of the prototype for the new magnet control via VME • Get an estimate of possible switchover later in the year Significant amount of work involved – but can (should) be done Mid-way towards the startup – gives time to correct things in case of problems

  16. Where do we stand (6/6) Beam startup or later : What remains to be tested • Installation and configuration of the PCs in the user barracks • Magnet control • Delestage – if considered useful (most likely not!) • Control of the large spectrometers for the experiments • Degauss GUI before loading new settings • CEDAR counters for particle ID • Requested by NA48/3 and ATLAS • Utilities for the operations within CESAR • Info publishing on the fixed displays ; alarms (using LASER) • Readout of radiation monitors • Surveillance programs for the target (wobbline) or the beam line (P0 survey) • Logging and browsing and use of a QUERY tool • Browsing and update tools for the configuration database

  17. Critical Issues • Expert Diagnostic tools • Parts exist; should get used to new environment having to combine information from different sources: CESAR GUIs, FESA navigator, … • Maintenance and support for non renovated equipment • Some critical ones like collimators still on SL-Equip • Can be accessed directly from CESAR using CMW gateway but not with FESA • Support for NODAL software still needed for some expert applications • Control and readout of CEDAR counters on critical path • Requested by NA48/3 and ATLAS • Possibility to satisfy the request but in “non standard” way • Operation • Adopt to the new CCC environment

  18. PS EAST Area • No modifications since 2004 • Modifications to primary zone discussed elsewhere (T.Zickler’s talk) • Problem with dipole in T9 limiting the beam energy to 10 GeV (instead of nominal 15) still to be investigated and probably fixed?? • Must experience the new “remote” operation • Renovation project to follow that of North Area • New hardware for beam instrumentation • Move to “CESAR like” environment

  19. AD Experimental Hall • The ATHENA collaboration does not exist any more and the zone is from this year taken over by ALPHA who will continue physics working on a second generation trap. • The beamlines still have the old MWPC:s which are destructive and slow. • The non-destructive pickups that were needed in view of operating from CCC have not been built

  20. Summary • A first HW test of two beam lines (H2 and H4) – Dry Run-1 - was successfully realized in November 2005 • All the available (at that time) HW and SW was tested under realistic conditions and valuable feedback to was given to the developers. • The next milestone is Dry Run-2 scheduled for end March 2006 • Test the whole North Area beam lines • Almost complete test of all equipment and functionalities • First test of new magnet control under VME • Due to the large number of HW changes, the long shutdown, and the reduced resources available, the “Wet Run”(i.e. Commissioning with beam) before the Physics starts is mandatory • No show-stoppers identified so far but still lot of work ahead!!! Many thanks to all participants for their continuous efforts

More Related