1 / 8

Digitizer Status

Digitizer Status. Tilecal Institute Meeting 03-02-18. Outline The TTCrx grounding problem The BCID readout problem Production time schedule. The TTC grounding problem Some missing ground connections on the TTC-rx gave rise to intermittent errors.

egil
Télécharger la présentation

Digitizer Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Digitizer Status Tilecal Institute Meeting 03-02-18 C.Bohm, K.Jon-And

  2. Outline • The TTCrx grounding problem • The BCID readout problem • Production time schedule C.Bohm, K.Jon-And

  3. The TTC grounding problem • Some missing ground connections on the TTC-rx gave rise to intermittent errors. • Problem not discovered in Stockholm due to low read out rate of test bench. • After grounding the open inputs the faults disappear. • Action: • 4 open inputs must be grounded on all boards • A new Stockholm test bench is being built to discover these kind of errors C.Bohm, K.Jon-And

  4. Action plan: • Fix 700 not mounted boards. • Print a modified pattern onto already manufactured boards using thick film techniques, then mount the boards as usual. Procedure should be verified within a week. • Fix 1400 already mounted boards. A more difficult problem. Done partly at our institute in parallel with testing above 700 boards, partly by a vendor: C.Bohm, K.Jon-And

  5. Repair plan of mounted boards Desolder TTCrx from the boards. Done in our institute. Rather easy, 2 minutes per board (in total about 50 hours). Remove solder. Done in our institute. More difficult, 6 minutes per TTCrx (in total about 140 hours). Print grounding pattern on bottom of TTCrx.30 seconds per board. Done by us at M A Kapslingsteknik. Harden the conductive paste in a nitrogen oven. At Ericsson once per day. Done by M A Kapslingsteknik. Reballing the TTCrx. 9 at a time into the oven. Done by M A Kapslingsteknik. Remounting the TTCrx. Perhaps 10 minutes per board. Done by us in collaboration with SMD production, our mounting vendor (in total about 240 hours). Two persons at our institute work half time about 11 weeks. C.Bohm, K.Jon-And

  6. BCID read out problems • At the recent TileCal expert week it was found that the BCID readings were unreliable. • This was found to be due to set-up and hold time violations which occurred since the output timing of the TTCrx chip was changed between different batches. • In the electronics meeting 4 different remedies were suggested: • Change of a clock driver to a faster component (“driver solution”) • Resistor delay clk_des_1 (not preferred) • Capacitor delay clk_des_1 (not preferred) • Replace clk_des_1 with clk (“clock solution”) C.Bohm, K.Jon-And

  7. Comparison of ”driver” and ”clock” solution • ”Driver”-solution • Recent tests indicate time budget is safe. Time margin in worst case w.r.t. TTCrx clock is 1.3 ns. • Some more tests are needed, e.g. with LV and temperature variations. • Clean easy ”patch” (change a component). • New components have to be burnt-in and radiation tested. • ”Clock”-solution • Safe timing solution. • Patch not as clean as for driver. • Incompatible with Sthlm link interface used in Sthlm. Takes 1 month to change interface. C.Bohm, K.Jon-And

  8. Tentative time schedules 3/3 Decision of BCID solution ”Driver”-solution 14/3: 20 boards QC and sent to ”expert week”. 21/3: 20 boards to C-F if OK. 24/3: 20 ”printed” boards to C-F 14/4: 50 boards to C-F 21/4: 50 boards to C-F 28/4 … 100 boards per week. ”Clock”-solution” 7/3: 20 boards to ”expert week” before QC 11/4: 20 QC boards to C-F. 14/4: 20 ”printed” boards to C-F 5/5: 50 boards to C-F 11/5: 50 boards to C-F 18/5 … 100 boards per week. N.B. These are AGRESSIVE time schedules. C.Bohm, K.Jon-And

More Related