1 / 10

Elementary 33 Construction Update

Elementary 33 Construction Update. June 27, 2013. Michael E Finn. Overview. Preconstruction Phase General Specifications of Plans Milestones Site and Floor Plans. Preconstruction. Drawings Conceptual drawings completed Construction documents completed by July 1

ekram
Télécharger la présentation

Elementary 33 Construction Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Elementary 33 Construction Update • June 27, 2013 Michael E Finn

  2. Overview • Preconstruction Phase • General Specifications of Plans • Milestones • Site and Floor Plans

  3. Preconstruction • Drawings • Conceptual drawings completed • Construction documents completed by July 1 • Plan submitted to city by July 8 • Subcontractors selected and Guaranteed Maximum Price by August 1 • Permits issued by September 13

  4. Hurdles in Preconstruction • Vehicle queuing and site layout • Significant adjustments made to accommodate city requirements for queuing and traffic • Questions regarding zoning and the application of zoning to School Districts • Open item and all parties continue to work with the city • Total project expense • Many adjustments have been made to reduce expenses • Project still over $16M budget • Adjacent ways funds to bridge the gap

  5. General Specifications of Site • Total space of 96,000 square feet in 2 main buildings • Gymnasium remains separate from dining area • Gymnasium/Dining wing 23,200 square feet • Educational wing 72,800 square feet • Classrooms • 4 classrooms per grade • 970 square feet K-3 • 850 square feet 4-8

  6. Milestone dates • Permits issued by the city – September 13 • Ground breaking ceremony – August 21 • Leadership for site announced – January • Positions filled for 2014-2015 School Year - June • Certificate of occupancy issued – July • FF&E completed - July • Doors open for employees - August • Doors open for students - August

  7. Site Plan April 2013

  8. New Site Plan 6-10-13

  9. Page of Floor Plan 6-10-13

  10. Questions

More Related