1 / 2

RHIC Status Update

Progress of beam work Four scheduled shifts with beam so far Established captured beam with good lifetime (snakes on) and the bulk of instrumentation setup in the first three Lost the last of the four to 9 MHz failure Power supply progress

emmet
Télécharger la présentation

RHIC Status Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Progress of beam work • Four scheduled shifts with beam so far • Established captured beam with good lifetime (snakes on) and the bulk of instrumentation setup in the first three • Lost the last of the four to 9 MHz failure • Power supply progress • Blue delivered for injection 1 day early (Thanks, Don and co.!) • Yellow ready for injection tonight • Blue through 100 GeV hysteresis by tonight • Still planning on finishing p.s. work on 1/28. • RF work • Blue capture on new LLFR took 1 shift (as estimated, Thanks Alex and Kevin and co.!) RHIC Status Update Time Meeting, V. Schoefer 1/24/12

  2. RHIC Status Update Time Meeting, V. Schoefer 1/24/12 • To be done this week • At injection • Repeat the above with yellow • Finish instrumentation setup in blue • Orbit feedback tests • 10 Hz feedback tests • BPMs to fixed trigger • CNI setup in both rings • Prepare for ramping • Finish power supply work (inluding DX training) • Setup and commissioning of new LLRF loops • Begin 100 GeV ramp development

More Related