20 likes | 120 Vues
Last week focused on raising bunch number and rebucketing progress. Key highlights include energy storage mechanics, transmission efficiency over 98%, and 65% polarization at flattop. Challenges with 109-on-109 setups noted in RHIC status update meeting. Re-commissioning LLRF planned, with AC and RF issues being addressed. Stay tuned for more updates on beam operations.
E N D
Spent most of last week raising the bunch number and setting up rebucketing • Progress of beam work • Energy and storage ramp mechanics are worked out • Transmission efficiency > 98% • Polarization ~65% at flattop • Currently working on getting through rebucketing with high bunch number • Losses with 109 on 109 pull the permit RHIC Status Update Time Meeting, V. Schoefer 2/7/12
RHIC Status Update Time Meeting, V. Schoefer 2/7/12 • Speed bumps • Rebucketing setup took somewhat longer than expected • Essentially re-commissioning LLRF this year • Several trips of x-arc due to AC problem in 1000P • Cryo software and communication problem • Frequent trips of the 9 MHz RF while at store • Cavity trips due to a very fast rise in vacuum. Not explained yet • Yellow carbon polarimeters are swamped with noise after rebucketing. • Blue and yellow bunch distributions are the same