1 / 19

The KINGDOM OF MOROCCO Ministry of Land-Use Management, Water and the Environment

The KINGDOM OF MOROCCO Ministry of Land-Use Management, Water and the Environment Secretary of State for the Environment. CD CDM - MOROCCO 2003 Realizations and 2004 Activities Program CD CDM Project Ali Agoumi ; National Coordinator. CDM-Morocco.

ernst
Télécharger la présentation

The KINGDOM OF MOROCCO Ministry of Land-Use Management, Water and the Environment

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The KINGDOM OF MOROCCO • Ministry of Land-Use Management, Water and the Environment • Secretary of State for the Environment CD CDM - MOROCCO2003 Realizations and2004 Activities ProgramCD CDM ProjectAli Agoumi ; National Coordinator CDM-Morocco

  2. ContentsI - Climate Protection : The Ultimate Objective .………………. 4 II - CDM National Strategy… ……………………………………. 8III - CDM Designated National Authority Missions and Attributions ….…………….…….………….. 11IV –Project Evaluation and Approval Procedures ………………………………….…… 14Contents • I 2003 Project Launch • II 2004 Consolidation CDM-Morocco

  3. I- 2003 Project Launch -Development and implementation of the CDM national strategy for 2003-2005 (SOP) -The setting up of the CDM DNA along with its rules, procedures and functions(CDM NC and CDM PS: workshop in September and meeting on November) • Development of national CDM project evaluation and approval procedures (Adoption by the DNA in September ) • Development of national sustainable development criteria(Adoption by the DNA in November ) CDM-Morocco

  4. CDM DNA Activities • a regulation activity to set the CDM project evaluation and approval rules and procedures ; • a promotion activity centered on capacity building and marketing CDM DNA structure • a CDM National Council (CDM NC) • a Permanent Secretariat of the National Council (CDM PS) based at the Climate Change Unit; Secretary of State for the Environment. CDM-Morocco

  5. CDM NC Components - The Secretary of State for the Environment(President); - Ministry of Foreign Affairs and Cooperation - Ministry of the Interior - Ministry of Finance and Privatization -Ministry of Commerce, Industry and Telecommunications • - The Prime Minister’s Delegated Ministry of Economic and General Affairs and Economical Improvement - Ministry of Agriculture and Rural Development - Ministry of Equipment and Transport - Ministry of Energy and Mines • -The High Commissariat of Water ,Forestry andCombating Desertification -The GCME (the General Confederation of Moroccan Enterprises), MCEP (the Moroccan Center of Export Promotion), REDC (the Renewable Energy Development Center), and MCCP (the Moroccan Center for Cleaner Production)  - From civil society. The participation of the public in this is assured by NGOs involved in combating CC impacts and/or in initiating SD programs. CDM-Morocco

  6. Approval and Evaluation Procedure of CDM Projects PIN received by the DNA Preliminary Evaluation Based on the PIN (response announced by the DNA: maximum within 2 weeks) In-depth Evaluation Based on the PDD (response transmitted by the DNA: maximum within 4 weeks) not accepted Approval letter delivered to the project promoter by the Moroccan DNA CDM-Morocco

  7. National Sustainable Development Criteria -The project must be integrated into a developing country’s main objectives and be a part of the defined priorities in the National Sustainable Development Strategy. -The project must conform to current country laws and in particular the ones related to the environment and its preservation. It is particularly essential that an environmental impact study be realized in conformity with the national regulations on environmental impact studies. -The project must use clean and confirmed technologies and avoid any out-dated technologies. A list of indicators has been used to build a more precise criteria matrix for CDM Morocco project eligibility, in conformity with the national Sustainable Development policy. CDM-Morocco

  8. 2003 Project Launch!! - Supporting three economic operators at a chosen level and the development of three pilot project design documents of which they are the promoters: • - ONE; Essaouria wind Park • - OCP; Jorf Lasfar HRS OCP unit • - Rabat Local Council: Akreuch Waste discharge -Continued training effort, starting in the UNDP-GEF RAB project framework, on the development of CDM project PDDs( workshop on 1st July 2003) CDM Morocco Expert Network CDM-Morocco Avec le soutien du PNUD et du PNUE

  9. IV First CDM Moroccan Projects approved by the DNA:1st Project Project Title: Rehabilitation of the landfill in Akreuch as a landfill gas to energy project. Project developer:City Council of Rabat Type of project:Methane recovery in the waste sector • Technical and financial components of the project: • Project development costs: 0.05 million $US • Installation costs: 0.80 million $US •  Costs of realisation of the project : 0.85 million • US$, 100% self-financed • Annual operation costs: 0.055 million $US • Estimate of GHG emission reductions:1.59 million tonnes of CO2eq. over 21 years • Estimated carbon revenues from the project: 4.77 millions de $US

  10. IV First CDM Moroccan Projects approved by the DNA:2nd Project Project title : Heat recovery enhancement for power generation at the Maroc Phosphore’s phosphoric acid and fertilizer production plant of Jorf Lasfar, Morocco Project developer:Office Chérifien des Phosphates Type of project : Energy efficiency in the industrial sector • Technical and financial components of the project: • Project development costs: 2.5 million $US • Installation costs: 1.75 million $US • Annual operation costs: 0.75 million $US • Total project costs: 20 million $US, 100% financed by OCP • Estimate of GHG emission reductions: 888,813 tonnes of CO2eq. over 10 years • Estimated carbon revenues from the project: 3.55 millions de $US

  11. IV First CDM Moroccan Projects approved by the DNA:3rd Project Project title : Wind Park Essaouira Project developer: Office National d’Electricité (ONE) Type of project : Renewable Energy production • Technical and financial components of the project: • Project development costs: 1.2 million $US • Installation costs: 88.7 million $US • Total project costs: 88.9 million $US, financed by ONE and KfW. ONE is still looking for other investors in the project • Estimate of GHG emission reductions: 1.62 million tonnes of CO2eq. over 10 years • Estimated carbon revenues from the project: between 8 and 13 millions de $US

  12. 2003 Project Launch!! -The initiation of a national and international communication action on CDM Morocco, in particular through: • -Developing CD CDM Morocco project brochures - Setting up a CDM Morocco web site www.mdpmaroc.com - Publishing CDM Morocco ECHOS MDP - The participation of project staff in different national and international demonstrations or the project activities which were presented a OS18, COP9 ... COP9 UNDP and UNEP side events CDM-Morocco

  13. 2003 Project Launch!! • -The launch of three studies on the following aspects: - Morocco’s institutional investment framework and the promotion of CDM • - CDM Morocco’s training plan for 2004-2005 • - CDM Morocco’s communication programme and actions Results available at the end of the first semester of 2004 !!!! CDM-Morocco

  14. II- 2004  Consolidation Programme!!! 1 Objectives: • - Pursuit of strategy implementation • - Refining and better precision the project activities * Studies • Monitoring and starting to implement recommendations and proposals from ongoing studies in 2003 on: • Investment • Training • Communication CDM-Morocco

  15. II- 2004  Consolidation Programme!!! 2 §-SETTING UP SMALL SCALE PROJECTS -Three national economic operators will be accompanied by the project for the development of PDD for its small projects -A training workshop for the attention of research experts and consultants on the setting up of small scale CDM projects is anticipated National Consultants ! CDM-Morocco

  16. II- 2004  Consolidation Programme!!! 3 NATIONAL WORKSHOPS *(1) January 2004: Workshop on the baselines - target group: research experts and consultants - animation : Ecosecurities, RISOE and project RC (2) February 2004: CDM Information workshop - target group: banks, financial organisations and credit companies - animation : project staff, RISOE and project RC (3) March 2004: Workshop on institutional aspects - target group: CDM NC, CDM PS - animation : project staff, RISOE and project RC CDM-Morocco

  17. II- 2004  Consolidation Programme!!! 4 NATIONAL WORKSHOPS (4) April 2004: NATIONAL CDM FORUM - target group: EO, investors, research experts and consultants, NGOs - animation: Ecosecurities, RISOE, project RC and project staff (5) September 2004: Workshop on a small scale CDM projects development - target group: research experts and consultants - -animation: National consultants , RISOE, project CR and project staff +REGIONAL WORKSHOPS CDM-Morocco

  18. II- 2004  Consolidation Programme!!! 5 COMMUNICATION, AWARENES - CDM Morocco network support - web site www.mdpmaroc.com - CDM ECHOS bulletin - adapted packs and brochures - participation of members of the project staff in national and international demonstrations Study’s recommandations communication on CDM CDM-Morocco

  19. THANKs,www.mdpmaroc.com Climate Change Unit; Secretary of State for the Environment rcmdp@mtds.com

More Related