An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ACQUATICS FACILITY STUDY City of Vincennes Department of Parks & Recreation

  2. Concerns and Problems with Rainbow Beach • Overall image is poor, facility is tired and no longer an attraction. The facility lacks vitality. • Visitors are being lost to other venues. • The condition of the bathhouse is substandard. • Without shade, the oversized concrete pool deck is oppressive in the summer heat. • Pool mechanical system is antiquated and is past its life expectancy. • The concrete deck all around the pools has an irregular surface at expansion joints and settlement cracks. • Water from both the competition and wading pools is circulated through a single circulation pump violating current swimming pool codes. • Maintaining chemical balance for this pool is difficult. • It is reported that the pool loses approximately 1”-2” of water overnight due to leaks in the pool system located under the concrete pool shell. City of Vincennes – Aquatic Facility Study

  3. Recommendations 1. Slides and / or Diving Boards 2. Play Apparatus / Structure for all ages 3. Zero Depth Entry 4. Competition / Recreation Combination – Uniqueness of 50 Meter Pool 5. Upgraded Bathhouse 6. Improved Concessions 7. ADA Accessibility 8. Variety of Experiences – Water Basketball, Water Volleyball, Etc. 9. Shade Structures and Lounge Seating 10. Sound System and Wi-Fi 11. Planned Activities and Programs City of Vincennes – Aquatic Facility Study City of Vincennes – Aquatic Facility Study City of Vincennes – Aquatic Facility Study

  4. Pool Amenities City of Vincennes – Aquatic Facility Study

  5. Slides City of Vincennes – Aquatic Facility Study

  6. Zero Depth Entry City of Vincennes – Aquatic Facility Study

  7. Shade Structures City of Vincennes – Aquatic Facility Study

  8. Play Apparatus City of Vincennes – Aquatic Facility Study

  9. Spray Parks City of Vincennes – Aquatic Facility Study

  10. Recreation/Competition Combination City of Vincennes – Aquatic Facility Study

  11. Bathhouse, Locker Facilities and Party Facilities City of Vincennes – Aquatic Facility Study

  12. Options for Rainbow Beach City of Vincennes – Aquatic Facility Study

  13. Option A: Addition of a spray park to the existing facility City of Vincennes – Aquatic Facility Study

  14. Option A: Addition of a spray park to the existing facility • Description and Cost • Existing Recreation Pool and Bathhouse to Remain…………………….....................…....... • Remove existing Wadding Pool and Deck………………………………………………………….…. • Create New Splash Park………………………..…………………………………………………………… • Provide Associated Site Improvements…………………….…………………………………….….... • Shade Structures, Pavement, Fencing, Etc. • Contractor General Conditions/Overhead & Profit…………………………………………..……….. • Construction Range of Magnitude Budget………………..…………………………….….…….. • Add new deck around the existing pool…………………………………………………………….……. • 0 • 10,000 • 140,000 • 85,000 • 22,000 • 257,000 • ????? • $ • $ • $ • $ • $ • $ City of Vincennes – Aquatic Facility Study

  15. Option B: Renovation of the existing facility City of Vincennes – Aquatic Facility Study

  16. Option B: Renovation of the existing facility • Description and Cost • Minor Renovations to Existing Bathhouse.……………….…......................................... • Renovation Existing 10 Lane 50 Meter Lap Pool………………....…………………............. • Infill Diving Well, Create New Slide Well, Create Zero Depth Entry, • New Pool Filtration & Chemical Systems, Piping & Equipment • Demolition, New Equipment Building, MEP, Pool Deck, Fencing & • Shade Structures……………….…………….………………………………………………..…......… • Provide New Water Slide…………………………………………………………………………....... • New Water Features/Play Apparatus……………………….………………………………...….. • Contractor General Conditions/Overhead & Profit.………………………………………..…. • Construction Range of Magnitude Budget……….………………………………….........… • $ • $ • $ • $ • $ • $ • $ • 100,000 • 1,800,000 • 810,000 • 175,000 • 165,000 • 305,000 • 3,355,000 • -$300,000 • -$3,480,000 City of Vincennes – Aquatic Facility Study

  17. Option B.1: Renovation of the existing facility City of Vincennes – Aquatic Facility Study

  18. Option B.1: Renovation of the existing facility • Description and Cost • Minor Renovations to Existing Bathhouse………………….…..................................... • Renovation Existing 10 Lane 50 Meter Lap Pool………………....…………………......... • Infill Diving Well, Create New Slide Well, Create Zero Depth Entry, • New Pool Filtration & Chemical Systems, Piping & Equipment • Demolition, New Equipment Building, MEP, Pool Deck, Fencing & • Shade Structures……………………………………………………………………………………... • Provide New Water Slide…………………………………………………………………………... • New Water Features/Play Apparatus.……………………………………………………….... • Add Spray Park and Associated Site Improvements………………………………………. • Contractor General Conditions/Overhead & Profit…………………………………..…… • Construction Range of Magnitude Budget………………………………………..…….… • $ • $ • $ • $ • $ • $ • $ • $ • 100,000 • 1,800,000 • 810,000 • 175,000 • 165,000 • 160,000 • 321,000 • 3,531,000 • -$300,000 • -$3,656,000 City of Vincennes – Aquatic Facility Study

  19. Option C: Construction of a replacement facility City of Vincennes – Aquatic Facility Study

  20. Option C: Construction of a replacement facility • Description and Cost • Minor Renovations to Existing Bathhouse…………………………….…..................... • Create New Pool………………………………………………………………....……….......... • Eight Lane – 25 Yard Lap Pool, Zero Depth Entry, • Slide Well, New Pool Filtration & Chemical Systems, • Piping & Equipment • Demolition, New Equipment Building, MEP, Pool Deck, Fencing & • Shade Structures, etc…………………………………………………………..………………... • Provide New Water Slide………………………………………………………..................... • New Water Features/Play Apparatus……………….…………………….………………... • Contractor General Conditions/Overhead & Profit………………….………............ • Construction Range of Magnitude Budget…………………………….................... • 100,000 • 1,250,000 • 740,000 • 175,000 • 165,000 • 243,000 • 2,673,000 • $ • $ • $ • $ • $ • $ • $ • -$300,000 • -$2,798,000 City of Vincennes – Aquatic Facility Study

  21. Option C.1: Construction of a replacement facility City of Vincennes – Aquatic Facility Study

  22. Option C.1: Construction of a replacement facility • Description and Cost • Minor Renovations to Existing Bathhouse…………………………….…..................... • Create New Pool………………………………………………………………....……………… • Eight Lane – 25 Yard Lap Pool, Zero Depth Entry, • Slide Well, New Pool Filtration & Chemical Systems, • Piping & Equipment • Demolition, New Equipment Building, MEP, Pool Deck, Fencing & • Shade Structures, etc…………………………………………………………..……………….. • Provide New Water Slide………………………………………………………................... • New Water Features/Play Apparatus…..………………………………….……………….. • Add Spray Park and Associated Site Improvements…………………………………… • Contractor General Conditions/Overhead & Profit………………….………………… • Construction Range of Magnitude Budget…………………………….................... • $ • $ • $ • $ • $ • $ • $ • $ • 100,000 • 1,250,000 • 740,000 • 175,000 • 165,000 • 160,000 • 259,000 • 2,849,000 • -$300,000 • -$2,974,000 City of Vincennes – Aquatic Facility Study

  23. Option C.2: Construction of a replacement facility City of Vincennes – Aquatic Facility Study

  24. Option C.2: Construction of a replacement facility • Description and Cost • Minor Renovations to Existing Bathhouse…………………………….…............ • Create New Pool………………………………………………………………....……… • Eight Lane – 50 Meter Lap Pool, Zero Depth Entry, • Slide Well, New Pool Filtration & Chemical Systems, • Piping & Equipment • Demolition, New Equipment Building, MEP, Pool Deck, Fencing & • Shade Structures, etc…………………………………………………………..……….. • Provide New Water Slide………………………………………………………........... • New Water Features/Play Apparatus…..………………………………….……….. • Add Spray Park and Associated Site Improvements………………………….. • Contractor General Conditions/Overhead & Profit………………….……….. • Construction Range of Magnitude Budget…………………………….......... • $ • $ • $ • $ • $ • $ • $ • $ • 100,000 • 2,300,000 • 810,000 • 175,000 • 165,000 • 160,000 • 371,000 • 4,081,000 • -$300,000 • -$4,206,000 City of Vincennes – Aquatic Facility Study

  25. Option C.3: Construction of a replacement facility City of Vincennes – Aquatic Facility Study

  26. Option C.3: Construction of a replacement facility • Description and Cost • Create New Pool………………………………………………………………....………… • Eight Lane – 50 Meter Lap Pool, Zero Depth Entry, • Slide Well, New Pool Filtration & Chemical Systems, • Piping & Equipment • New Equipment Building, MEP, Pool Deck, Fencing & • Shade Structures, etc…………………………………………………………..………….. • Provide New Water Slide………………………………………………………............. • New Water Features/Play Apparatus………………..……………………………….. • Add Spray Park and Associated Site Improvements…………………………….. • Add New Bathhouse with Concessions………………………………………………. • Contractor General Conditions/Overhead & Profit………………….………….. • Construction Range of Magnitude Budget……………………………............. • 2,300,000 • 810,000 • 175,000 • 165,000 • 160,000 • 625,000 • 423,000 • 4,658,000 • $ • $ • $ • $ • $ • $ • $ • $ • -$300,000 • -$4,783,000 City of Vincennes – Aquatic Facility Study

  27. Cost Comparison City of Vincennes – Aquatic Facility Study

  28. Cost Comparison of Other Facilities City of Vincennes – Aquatic Facility Study

  29. Cost Comparison of Other Facilities City of Vincennes – Aquatic Facility Study

  30. Cost Comparison of Other Facilities City of Vincennes – Aquatic Facility Study

  31. Questions?