Coastal Protection and Restoration Authority (CPRA) Office of Coastal Protection and Restoration

Coastal Protection and Restoration Authority (CPRA) Office of Coastal Protection and Restoration. Lands, easements, rights-of-way and relocations (LERRD’s) Up date on Flood Protection and Levee Projects. Office of Coastal Protection and Restoration.

Télécharger la présentation

Coastal Protection and Restoration Authority (CPRA) Office of Coastal Protection and Restoration

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Coastal Protection and Restoration Authority(CPRA)Office of Coastal Protection and Restoration Lands, easements, rights-of-way and relocations (LERRD’s) Up date on Flood Protection and Levee Projects

  2. Office of Coastal Protection and Restoration • Non Federal Sponsor (CPRA) responsible for $300 million of (LERRDS) • Right of Way Conference was held on February • Representatives present: • USACOE • OCPR • SLFPA-W • SLFPA-E • DOTD • Determine Roles • Determine path forward and funding mechanisms • Standardize procedures across Levee Districts • Put together a game plan to meet schedules and budgets • Utilize Levee District Strengths • Augment with contractors

  3. Office of Coastal Protection and Restoration UPDATE FOR SLFPA –W WEST JEFFERSON LEVEE DISTRICT AND ALGIERS LEVEE DISTRICT • Continue to grant Right of Entry (ROE)/Authorization for Entry (AFE) through Levee Districts ( 22 by the end of August) • Number of reaches: 32 • Relocation of Utilities, pipelines, highways (115)

  4. Office of Coastal Protection and Restoration UPDATE FOR SLFPA –E PONTCHARTRAIN LEVEE DISTRICT • Continue to grant ROE/AFE through Levee Districts (granted 4 AFE’s for construction) • Number of reaches: 17 • Relocation of Utilities, pipelines, highways (25)

  5. Office of Coastal Protection and Restoration UPDATE FOR SLFPA –E EAST JEFFERSON LEVEE DISTRICT • Continue to grant ROE/AFE through Levee Districts (granted 6 AFE’s for construction) • Number of reaches: 15 • Relocation of Utilities, pipelines, highways (39)

  6. Office of Coastal Protection and Restoration UPDATE FOR SLFPA –E ORLEANS LEVEE DISTRICT • Continue to grant ROE/AFE through Levee Districts (granted 7 AFE’s for construction) • Number of reaches: 18 • Relocation of Utilities, pipelines, highways (56) • Property exchange with USF & WS

  7. Office of Coastal Protection and Restoration UPDATE FOR SLFPA –E LAKE BORGNE LEVEE DISTRICT • Continue to grant ROE/AFE through Levee Districts (4 pending for construction) • Number of reaches: 7 • Relocation of Utilities, pipelines, highways (33)

  8. Office of Coastal Protection and Restoration BIG PICTURE ISSUES • Acquisitions are on going (a lot of moving parts) • Borrow sites • Highway Crossings • Schedules • Most of this work will be done within 12 months • LERRDS for mitigation • Opportunities for Credit

  9. Office of Coastal Protection and Restoration Questions?