1 / 9

THEMIS Mission Confirmation Readiness Review Peter R. Harvey University of California - Berkeley

THEMIS Mission Confirmation Readiness Review Peter R. Harvey University of California - Berkeley. Issue#1. Staffing. GSFC-Required Additional Management UCB Has Complied with Additional Personnel Swales/Hammers Oversight: Dave King (fmr GSFC/JSC Shuttle)

gezana
Télécharger la présentation

THEMIS Mission Confirmation Readiness Review Peter R. Harvey University of California - Berkeley

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. THEMIS Mission Confirmation Readiness • Review • Peter R. Harvey • University of California - Berkeley

  2. Issue#1. Staffing • GSFC-Required Additional Management • UCB Has Complied with Additional Personnel • Swales/Hammers Oversight: Dave King (fmr GSFC/JSC Shuttle) • Mission I&T : Rick Sterling (RHESSI) • SE Oversight : • - Thermal : Paul Cleveland (GSFC, RHESSI) • - Software: Dave King / Will Marchant (EUVE, ChipSat) • - I&T : Terry Sharton (JPL retired, RHESSI) • ISM : Peter Berg (RHESSI) • IDPU Dev Lead: Michael Ludlam (Rosetta)

  3. Issue#2. Instrument Schedules • Add Detail to Instrument Schedules • Continued to Detail Schedules (Definition & Resources) • Worst Instrument Schedule (ESA) • Added Instrument Manager (C. Scholz) • Had n tasks, Now has M tasks • At PDR, the instrumentation used 13 schedules, 1417 tasks • Currently, we use 20 schedules, 2121 tasks • Resource loading being added as time permits. Schedule Maintenance • Instrument Developers Report to Their Schedule Weekly • 1 Full-Time Scheduler for Instrumentation • Provides Status to Project Management & Mission Manager

  4. Issue#3. Contracting • Impacts of Delayed GSFC-UCB Contract • GSFC-UCB Contract Definitized December 2003 • UCB-Swales subcontract work agreed by all parties • Implement subcontract value per CSR proposal • Add Swales-developed CPU card as mod 1 • Subcontract Expected in February timeframe • Contract Delay has had no known cost or schedule impacts to reserves.

  5. Issue#4. Risk • Develop Integrated Risk Management • GSFC Provided Risk Management Training to UCB Jan 2004 • THEMIS Risk Management Plan Submitted Jan 2004 • UCB/Swales Risk Lists Integrated and Provided to Explorers

  6. Issue#5. Separation System • Expedite Separation System Development • Prioritizing the Separation System tests at Swales • Long Lead Item (NSI’s) are currently critical path. • Review of Test Plan Considered Essential to the Effort

  7. Issue#6. Orbit Debris • Expedite ODA Issue Resolution • Submitted Orbit Debris Analysis Results • Lower Perigee Option Helps but may Impact Science • Studies with KSC and Boeing to Provide Possibilities • Examining Possible Options to Increase Reliability from 0.83 • Reliability of a Single-String Probe will Never be 0.99

  8. Issue#7. Instrument Thermal • Instrument Thermal Design • Instrument Thermal Design presented only at Peer Reviews    • Detailed thermal analyses have been completed for all instruments            • Currently on 3rd iteration of integrated instrument/spacecraft model            • Hot/Cold cases have been identified and are being used            • Board level thermal analyses are in progress    • Peer Review of instrument thermal design has been scheduled for last week in February    • Paul Cleveland (RHESSI) Providing Oversight of system level thermal design

  9. Issue#8. Monitoring Separation • Add Separation Monitoring for Probes 2-5 • Top Probe Will Transmit Separation in RealTime • All Other Probes Will Be Programmed to Monitor Probe Sep • Each Probe will have Gyros On • Replay of All Probes after Separation one at a time. • Details in MPDR RFA #17

More Related