1 / 23

Dale McMaster, President & CEO Alberta Electric System Operator November 2006

Alberta: Canada’s First Competitive Electricity Market. Dale McMaster, President & CEO Alberta Electric System Operator November 2006. Presentation Overview. An introduction to Alberta The structure of the electricity industry Transmission Policy and its implementation.

hasad
Télécharger la présentation

Dale McMaster, President & CEO Alberta Electric System Operator November 2006

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Alberta: Canada’s First Competitive Electricity Market Dale McMaster, President & CEO Alberta Electric System Operator November 2006

  2. Presentation Overview • An introduction to Alberta • The structure of the electricity industry • Transmission Policy and its implementation

  3. Alberta the Centre of Western Canada

  4. Alberta’s Electric Industry • More than 21,000 km transmission • Single control area of 660,000 km² • Interties to B.C. (up to 780 MW) & Sask. (up to 150 MW) • Over 280 generating units • 9,580 MW system peak • About 200 market participants • 11,734 MW internal generation capacity net to grid BC Alta Sask

  5. Alberta’s Electricity Generation Net to grid 5770 49% 4604 39% 899 .07% Wind 298 .03% Wood waste 133 0.1% Other 30 0.002% Total 11,734 (MW) (year-end 2005)

  6. Transmission Interconnections Import Export • British Columbia 0-780 0-800 MW • Saskatchewan 0-150 0-60 MW Note: Intertie capability varies with system operating conditions including the generation pattern

  7. Alberta Outlook: Load and Supply • A Bit of History: • More than 3,000 MW of new generation added to the system since 2001 • 4.2% average annual growth rate over the past five years for energy and peak demand • 4.9% year-to-date growth in energy • 10-year Outlook: 2007 to 2016 • 3% average annual growth rate in energy and peak demand • requirement for about 3,800 MW of new generation by 2016

  8. Competitive Restructuring Vertically Integrated Utility Functional Separation competitive forces Generation natural monopoly Transmission natural monopoly Distribution competitive forces Retail

  9. Evolution to Competition Timeline May 1995 June 1995 Jan. 1996 May 1998 June 1998 Aug. 2000 Jan. 2001 June 2003 Electric Utilities Act passed Independent Transmission Administrator appointed EUA takes effect Power Pool begins operation AESO formed PPAs go into affect Retail Competition begins Power Pool Council (PPC)formed Gov’t auctions rights to formerly regulated generator output (PPAs) Independent PPC & Market Surveillance Administrator appointed

  10. Alberta Industry Structure Electric Utilities Act Minister of Energy Appoints BP and AESOBoards, EUB Chairman & MSA Balancing Pool (BP) Alberta Electric System Operator Alberta Energy & Utilities Board (EUB) Regulates AESO’s Transmission business Market Surveillance Administrator (MSA) Wholesale Energy Market Transmission System Development and System Access Service System Operator

  11. The AESO: Background • Created as part of electric industry restructuring • Our mandate is defined by legislation • Do not own transmission or generation assets • Independent of industry (no commercial interests) • “not - for - profit” organization • Act in the public interest • Our mission: The AESO facilitates a fair, efficient, openly competitive and sustainable market for electricity and provides for the safe, reliable and economic operation of the Alberta Interconnected Electric System.

  12. The AESO: Core Business • Develop and operate Alberta’s real-time electric energy market • Facilitate the fair, efficient and openly competitive market for electricity • Direct the operation of Alberta’s power grid to ensure reliability • Plan development of Alberta’s transmission system to ensure reliability and to facilitate the competitive market and investment in new supply • Provide system access for both generation and load customers

  13. Transmission System Roles Transmission Facility Owners AESO

  14. Energy & Utilities Board (EUB) • The EUB is an independent, quasi-judicial agency of the Alberta government • Regulatory oversight of: • transmission system development • transmission system access • AESO transmission tariff • AESO “own costs” and cost of ancillary services and system losses • TFO facility and operating costs • generation projects • environmental and siting approvals

  15. Transmission Policy: Drivers for change… • Alberta relies on the competitive market to provide investment for new generation • Only one significant transmission line built in the last 20 years • A once robust transmission system becoming inadequate • Increasing transmission congestion: • System losses and the associated costs • System reliability – voltage stability • Reliance on Transmission Must Run (TMR) generation – excessive costs and distortion of the price signal • Compromising the competitive energy market • Impediment to the investment in new supply • Potential impact on the economy of Alberta

  16. Why was this happening? • Expectation – “the market” would drive the development of the transmission system • The market signals weren’t adequate: • Postage stamp transmission tariff • “Energy only” real time pool market – single price • No significant locational signals -- i.e. no LMP • Ineffective system planning • Absence of decision making criteria • Chicken and egg conundrum • Resulted in an over reliance on location critical gas-fired generation and no new transmission • A clear government policy for transmission system development was required

  17. The Policy – an overview • Transmission planning must be proactive leading load growth and generation development -- market signals and/or congestion pricing schemes will not result in timely construction of transmission facilities • it is appropriate and necessary to align timelines, milestones and commitment of generation and transmission to ensure transmission is developed in a timely manner • preconstruction activities (planning, engineering and ROW) to be proactive and aggressive -- costs deemed to be necessary and prudent • actual construction to be timed with generation commitment and milestones to assure coincident completion

  18. The Policy cont’d… • Transmission must facilitate a competitive wholesale market – system must be reinforced such that about 95% of expected wholesale transactions can be realized without congestion • all in-merit generation can be dispatched and virtually all economic wholesale transactions may be realized without congestion under normal operating conditions

  19. The Policy cont’d… • Transmission development should eliminate the need for most Transmission Must-Run (TMR) Generation • TMR is not to be considered as a substitute for transmission development • ISO to be given flexibility to consider TMR where economic or an acceptable alternative to transmission • TMR costs to be based on “cost of service” model • Internal transmission should be reinforced to restore the existing inter-ties to their full import/export ratings • transmission internal to Alberta should be reinforced so that under normal conditions the existing interconnections can import and export on a continuous basis in accordance with design capability

  20. Since Policy Implementation… • AESO has about $1 billion in transmission investment approved and underway • Major Projects Approved: • 500 kV Edmonton to Calgary • SW System Reinforcement • City of Edmonton Reinforcement • NW System Reinforcement • Upwards of $3 billion in new transmission could be required in the next 10 to 15 years • Merchant Transmission – planning stage • Montana Alberta Tie Line • Northern Lights (major DC Transmission from Northern Alberta to the Pacific NW in USA)

  21. Summary • Industry/market structure established in 1996 and enhanced in 2003 has served Alberta well • Merging of the market and transmission functions within the ISO provided efficiencies • Independence of the transmission function is essential to develop competition for generation • System operation has remained reliable • The Transmission Policy has proven effective in advancing the “needs” approvals • The “energy only” market structure has provided sufficient incentives for investment in new supply

More Related