1 / 15

Risk Tracking

Risk Tracking. Group Members:. Kinza Hussain BSSE-F10-M-006 Madiha Malik BSSE-F10-M-017 Sanam Imtiaz BSSE-F10-M-022 Saeed Aalam BSSE-F10-M-016 Waseem Anjum BSSE-F10-M-020 Bilal Afzal BSSE-F09-M-034. Agenda:. Risk Management Process Why Tracking Risk Risk Tracking

hedy
Télécharger la présentation

Risk Tracking

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Risk Tracking

  2. Group Members: • Kinza Hussain BSSE-F10-M-006 • MadihaMalik BSSE-F10-M-017 • SanamImtiaz BSSE-F10-M-022 • SaeedAalam BSSE-F10-M-016 • WaseemAnjum BSSE-F10-M-020 • BilalAfzal BSSE-F09-M-034

  3. Agenda: • Risk Management Process • Why Tracking Risk • Risk Tracking • A Moving Target • Tracking Risk Response Plan

  4. Risk Management Process

  5. Why Tracking Risk? • Tracking involves reevaluation of all the risk attributes. The risk might have changed its attributes • Tracking risk intensity or exposure means that we assess risk probability and impact periodically • Both these characteristics may change with time

  6. Continue.. • If the risk occurred, we record it. If it has not occurred, we reassess the time of occurrence. • If the risk has been escalated or transferred, we trace the risk and check its status.

  7. Risk Tracking The risk tracking step monitors three main changes: • Trigger values - If a trigger becomes true, the contingency plan needs to be executed.  • The risk's condition, consequences, probability, and impact - If any of these change (or are found to be inaccurate), they need to be reevaluated.  • The progress of a mitigation plan - If the plan is behind schedule or is not having the desired effect, it needs to be reevaluated. 

  8. Continue.. This step monitors the above changes on three main time frames: • Constant - Many risks in operations can be monitored constantly or at least many times each day. For example, automated tools can monitor a Web server's bandwidth usage every few seconds.  • Periodic - IT operations stakeholders, especially those in the Service Role Cluster, periodically review the top risks list, looking for changes in the major elements. This often happens at staff meetings, change advisory board meetings, OMRs, and so on.  • As-needed - In some cases, someone simply notices that part of a risk has changed. This should still be tracked and recorded. 

  9. A Moving Target • Risk is a moving target. It has to be tracked • After mitigation, risks do not go away • The following steps help in tracking risks: • Phase-end risk reviews • Risk audits • Risk surveys • Project closure reviews • Risk-based estimation • Risk-based planning

  10. Continue.. • Designing the mitigation plan and actually mitigating the risk can be dramatically different • Mitigation brings us closer to risk • The true risk is seen only during mitigation and the true colors of perceived risks emerge during mitigation • When we track risks, we track the fusion of risk and risk perceptions

  11. Tracking Risk Response Plan • The goal of risk response planning is to come up with options and plans which will allow an organization to face threats which can reduce the likelihood of the project succeeding • Risk response options can be broken down into four methods, and these are: • Transfer • Mitigation • Acceptance • Avoidance • Responsibility of the project manager to decide the conditions for which strategies will need be used

  12. Continue.. • Risk response plans compete with the core project plans, unless both are integrated. • During tracking, we collect the following data: • Number of open risks • Number of plans that have not yet started • Number of plans in active progress • Number of completed plans • A simple form for tracking risk mitigation plans is given as follows:

  13. Risk mitigation plan tracking

More Related