The current status of the SDO (Solar Dynamics Observatory) reveals significant progress in integration, hardware orders, and development timelines. HMI, AIA, and EVE systems are fully integrated onto SDO, with the CPT process underway. Key milestones include delivery to KSC in August, readiness for launch by December this year, and a likely launch in January 2009. Development continues at JSOC, with new hardware expected to start operating by April. While DRMS/SUMS are nearing completion, export tools are slightly behind schedule. Level-0 completion is imminent, with Level-1 and Level-2 modules in progress.

iren
Télécharger la présentation

Update on SDO Status: Integration, Development, and Timeline for Launch

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SDO Status • HMI & AIA & EVE all integrated onto SDO • Doing “CPT” now. • PER 15 March • Deliver to KSC August • Ready for launch 1 Dec THIS YEAR • Likely launch still Jan ’09 • JSOC development continuing • Hardware ordered, some arrived, rest in March • New hardware operating by April • DRMS/SUMS nearing completion • Export tools lagging • Level-0 done soon (c. 2 weeks) • Level-1 getting started • Level-2 (pipeline modules) ready to get moving ASAP • Teams Meeting in March – register by 7 Feb. • Hope for “SDO Science Center” AO before March – NOT FINAL YET !!!

More Related