New Licensing System for Nuclear Reactor in Indonesia. Ai Melani¹*, Soon Heung Chang¹ ¹KAIST, *BAPETEN KNS Autumn Meeting,October 30, 2008. Contents. Introduction.

jafari
Télécharger la présentation

New Licensing System for Nuclear Reactor in Indonesia

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. New Licensing System for Nuclear Reactor in Indonesia Ai Melani¹*, Soon Heung Chang¹ ¹KAIST, *BAPETEN KNS Autumn Meeting,October 30, 2008

  2. Contents

  3. Introduction the Presidential Regulation No. 5 Year 2006 on National Energy Policy 2025 national electricity plan up to 2025 includes 2% nuclear energy options. one out of four NPPs be operated in the year 2016/2017.

  4. Background B A P E T E N SOCIETY REGULATION • Safety • Healt • Peacefull ACT No. 10/1997 LICENSING ENVIRONMENT INSPECTION • assure the welfare, the security and the peace of people; • assure the safety and the health of workers and public, and the environmental protection; • maintain the legal order in implementing the use of nuclear energy; • increase the legal awareness of nuclear energy user to develop a safety culture in nuclear field; • prevent the diversion of the purpose of the nuclear material utilisation; and • assure for maintaining and increasing the worker discipline on the implementation of nuclear energy utilisation. Function

  5. Why Should We Re-New? • The Nuclear Reactor Licensing System Based on Chairman of BAPETEN No. 06 year 1999. • It’s not match with Act No. 10 year 1997 require. • Indonesia Plan to build Nuclear Power Plant first NPP plant Will be operate on year 2017. • The Nuclear Reactor License Should be Renew. LAW Government regulations Presidential Decree Regulations of Chairman of Bapeten

  6. What is New on GR No. 43/2006 • 5 (Five) Step License : 1.Site License, 2. Construction License, 3. Commissioning License, 4. Operating License, 5. Decommissioning License • 3 (Three) Step License: 1.Site License, 2. Combined Operating License, 3.Decommissioning License

  7. Owner BAPETEN Other Agency Application to other Agency License from Other Agency PET & PJM-ET Evaluation Site Evaluation Permit Site Feasibility Studies LET DIQ dll. Evaluation Next Step Site License Site License Note : PET : Quality Assurance Program PJM-ET : QA Program for Site LET : Feasibility Studies Report DIQ : Information Quisionare

  8. Owner BAPETEN Ministry of Environment Site License from BAPETEN Review by Ministry Env. Env. Report LAKP LAKPr DID PJM-K dll. Environmental License Evaluation Construction Started Construction License Construction License Note: AMDAL : AnalisisMengenaiDampakLingkungan KPPA : KomisiPusatPenilai AMDAL LAKP : LaporanAnalisisKeselamatanPendahuluan LAKPr : LaporanAnalisisKeselamatanProbabilistik DID : DaftarInformasiDesain PJM-K : Program JaminanMutuKonstruksi

  9. Owner BAPETEN Construction Finished PKS ABD PKN PJM-KS BJF dll. Evaluation Commissioning License Commissioning started Commissioning License Note: PKS : Program Komisioning ABD : As-Built Drawing PKN : Program KesiapsiagaanNuklir PJM-KS : Program JaminanMutuKomisioning BJF : BuktiJaminanFinansial

  10. Owner BAPETEN Commissioning Finished LAKA LF-SBN PJM-O dll. Evaluation Operating License Operation Started Operating License Note: LAKA : LaporanAnalisisKeselamatanAkhir LF-SBN : LampiranFasilitas - Safeguard BahanNuklir PJM-O : Program JaminanMutuOperasi

  11. Owner BAPETEN Ministry of Environment Site License from BAPETEN Riview by Min. Env Env. Report SD LAK LAKPr DID PJM-KKO PKN dll. Environmental License Evaluasi Construction, Commisioning, and Operation Started Combined Operating License Combined Operating License Note: AMDAL : AnalisisMengenaiDampakLingkungan KPPA : KomisiPusatPenilai AMDAL SD : SertifikatDesain LAK : LaporanAnalisisKeselamatan LAKPr : LaporanAnalisisKeselamatanProbabilistik DID : DaftarInformasiDesain PJM-KKO : Program JaminanMutuKonstruksi s/d Operasi PJM-KKO : Program KesiapsiagaanNuklir

  12. Owner BAPETEN License is over/terminate PD PJM-D Evaluation Decommissioning Started Decommissioning License Decommissioning License Note: PD : ProgramDekomisioning PJM-D : Program JaminanMutuDekomisioning

  13. Termination of License • The termination of license, which is not applied for the site and decommissioning license, is subject to: • the expiration of the license; • the nuclear employer go bankrupt; • license revoking by BAPETEN; or • an application by the nuclear employers.

  14. Registration License Application Administrative Evaluation N Y Fulfill Administative requirement? Fulfill the Requirement Announcement Letter Y Technical review Verification N Y Further Improvement Evaluation Report Cost Payment Information to Pay License Cost License Accepted License Stipulated / Licensing Process LICENSE APPLICANT BAPETEN Fulfill Technical requirement?

  15. Conclusions • Indonesia is already prepares the new licensing system for nuclear reactor by issued Government Regulation No. 43 Year 2006. • Facing the first nuclear power plant construction, BAPETEN as soon as possible accelerates the establishment of regulations and guide to support the government regulations No. 43 Year 2006.