80 likes | 221 Vues
The Current NML layout measures 72 meters in overall building length, incorporating three cryomodules with feed and end cans spanning approximately 40 meters. Space constraints hinder the simultaneous installation of the photoinjector and downstream diagnostics prior to the beam dump. Initial decisions favor the installation of the first cryomodule, providing necessary space for both the photoinjector and the CCII. Critical components like modulators, klystrons, and control systems are under development, alongside ongoing networking tasks and equipment installation, targeting completion by December 2007.
E N D
Current NML Layout • Overall length of building is 72M • 3 cryomodules with feed and end cans ~40M • Not enough room for both photoinjector and downstream diagnostics before beam dump • Decision made to install first cryomodule with space for photoinjector and CCII • Physical layout of modulators and relay racks not yet determined • Network fiber to NML installation • Cryo fiber between lab B and NML – done • Fiber from NML to training center to mac room – in progress
Current NML Layout • Two 5MW Klystrons: RF gun and cryomodule • Embedded processor for modulator control and interlocks • eCos operating system with custom protocol for Epics interface • Beta version of Epics application ready • Two 500KW Klystrons: CCI (from photoinjector) and CCII • Modulator control needs interface • Possibly two low power 3.9 GHz klystrons
Current NML Layout • RF Interlocks • Embedded processor for control and interlocks • Testing/debugging at CCII • Will be used for 3.9GHz coupler conditioning test stand • Epics interface and conditioning sequencer
Current NML Layout • Cryo Controls • Existing GUI for various cryo subsystems at MDB. NML will be similar, need input from cryo people. • Have archive and plot applications, working on save/restore • LLRF • Simcon 3.1f (Fermi version) Gustavo Cancelo et al. • Doocs • Epics
Current NML Layout • The photoinjector at A0 • Most everything will be moved to NML • The control system (IRMs) does not necessarily move • 62 Power supplies: A/D, D/A, status, control • 66 Misc. A/Ds: vacuum, temperatures, etc. • 13 Stepping motors • 35 Digital control & status devices: flag actuators, gate valves, camera lights, video mux • 3 Servo motors: cave, laser, and transport iris • 20 Event plus delay timer/gate channels • 12 2MHz digitizer channels
Current NML Layout • The Schedule • First cryomodule arrives July 2007 • Cryo, vacuum, and RF interlocks controls available • RF interlocks commissioning and coupler conditioning (warm) into winter of 2007 • Dismantle/move photoinjector late summer 2007 • Gun will be ready ~December 2007 • Second cryomodule in 2008
Current NML Layout • Some Questions • Clock/Timing system • The existing clock system is adequate for initial conditioning. What are the requirements for NML? • Data acquisition and control • Power supply control • Danfysik power supplies for solenoids and spectrometer magnet • Generic A/Ds, stepping motors, gate valves, etc. • Special applications • Machine Protection System (MPS) • 40KW beam power can burn holes