1 / 17

Salsburgh WwTW Upgrade

Salsburgh WwTW Upgrade. Environmental Engineering Design Projects 4&5 2012-2013. Objectives. This course is intended to: encourage questioning and creative thinking develop skills in problem identification and solution development provide a realistic team working environment

jorryn
Télécharger la présentation

Salsburgh WwTW Upgrade

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SalsburghWwTW Upgrade Environmental Engineering Design Projects 4&5 2012-2013

  2. Objectives • This course is intended to: • encourage questioning and creative thinking • develop skills in problem identification and solution development • provide a realistic team working environment • develop skills of completing work on time and target • More specifically: • To give a realistic flavour of real design work in the UK Water Industry • To encourage and assess engineering communication of design ideas • Educational Benefit • ...is in doing the work, not in any marks gained!

  3. The Task • SalsburghWwTW is due for an upgrade • Salsburgh is in North Lanarkshire, quite close to Airdrie • Client is Scottish Water

  4. Background • Must gain an understanding of existing situation • How does the existing works function? • What are the problems with it? • Why is it being considered for upgrade? • What does the client want? • What does the client need? • CAPEX 1 • Design for option choice • Conceptually “30%” designed – ie, basic sizes of processes and how they fit, but not very detailed • CAPEX 2 • Design detailed enough for target cost calculation by Scottish Water • “70%” designed • Must clearly work in all aspects – hydraulics, site, foundation conditions, materials selected, power requirements, staffing required… • But not any structural design, no detailed drawings eg of pipe connections, specific M&E plant not completely defined…

  5. Basic Tasks • Week 1: Optioneering • Design at least 3 options to CAPEX 1 • Present and select a preferred option • Week 2: Detailed Design • Design preferred option to CAPEX 2 • Include concept, process design and drawings • Does not include any structural design

  6. Value Management Meeting • Standard public sector approach to option selection • Designers present a choice of options to various stakeholders • Scottish Water Management • Scottish Water Operations • SEPA • Local Authority • Perhaps others eg residents’ association, SNH, Forestry Commission, other developers • Stakeholders discuss, question, score and select preferred option for more detailed design • Each stakeholder has a different perspective • Scottish Water Management want least cost and least risk • Scottish Water Operations want easiest to maintain • SEPA want minimum environmental impact • Local Authority want a “politically acceptable” solution • Etc • Meeting needs to reconcile these • Lowest cost still almost always gets chosen – but not absolutely always… • Meeting may alter options and send you away with a new idea…

  7. Value Management Meeting Presentation • Existing works (1 slide) • Growth drivers (1 slide or combine with above) • Main problems to be addressed (1 slide) • Summarize options considered (1 slide) • Discarded options with reasons (1 or 2 slides) • Developed options (2 slides each for at least 3) • Plan • Advantages/disadvantages • Scoring (see below) • Each option must be a self contained solution for the whole works, but aspects can be repeated in more than one option if necessary

  8. Options Scoring Criteria • Planning and environment • Likely planning persmission problems? • Serious environmental impact? • Health and safety • During construction and operation • Maintenance and operations • Is the option going to be difficult to operate or maintain? • Design and process • Is it a proven process with this influent? • Does Scottish Water have previous experience of the process? • Buildability • Are there serious construction issues? eg site access? Component availability? • Likely cost • You cannot cost in detail – Scottish Water will do that – but it should be obvious when something is expensive relative to other options.

  9. Communication • Who is who, and how do they work? What do they already know? • Scottish water is an experienced and knowledgeable client, fully aware of all processes etc • Letters • Use correct format (see example) • Keep it brief – one page is best • Keep it clear – paragraphs, bullet points • Don’t write lecture notes! • Client relations • Efficient and business like communications are key • Drawing and sketching • See next slide • Spreadsheets • Widely used by Scottish Water and utility companies generally • See example • Calculations • See example • If using a spreadsheet, format as a calculation sheet and include formulae

  10. Drawing and Sketching • This is the main way engineers communicate • Increasingly, BIM and 3D visualization will play their part – but not for this project! • Drawings must be professionally prepared • Must have: • A border • A title block with title, number, date, revisions, author and checker information • A scale • Appropriate notes (eg “all dimensions in mm”) • Drawings attract most of the marks for this project and must be taken seriously • Improperly presented and insufficiently detailed drawings will attract fail marks…

  11. Method of Working • Work in groups of 2 or 3 • Group must be either all BEng or all MEng • Sign up for groups on Learn • Marks will be a group mark • Unless there are exceptional circumstances • Notify immediately if anything occurs eg illness • Clearly identify who did what as part of final submission

  12. Attendance Requirements • Tues 15th Jan 09:30-11:30 • Question and Answer Session • with Martin Pettinger from MWH (original design consultants) • Sanderson Building CR3 • Your chance to ask idiot questions… • Fri 18th Jan 09:00-15:00 (with breaks) • Value Management Meeting • With Martin Pettinger and Ian Lang from MWH • Groups take turns to present and score options • JCMB Teaching Studio 1206C

  13. Submission Requirements Week 1 • Tues 15th Jan 09:00 • Process Flow Diagram for existing works; and • Letter indicating your understanding of the main issues to be addressed • Thurs 17th Jan 09:00 • Plan drawings for at least three options with enough detail to identify process and layout of site • Fri 18th Jan 09:00- 15:00 • Value Management Meeting including your options presentation (presentation must be submitted after the meeting)

  14. Submission Requirements Week 2 • Tue 22nd Jan 09:00 • Completed options report with final scoring and preferred option from Value Management Meeting • Presented as an Excel Spreadsheet • Thur 24th Jan 09:00 • Process calculations including type of process, process flow, unit sizes and hydraulic s, showing head loss through works, pumping requirements etc • Presented as calculation sheets (can be suitably formatted spreadsheet) • Mon 28th Jan 09:00 • Final design • Must include plan, two sections across site, hydraulic profile and separate drawings for typical examples of each new process unit. • Covering letter of up to two pages summarizing the design and covering any key aspects that cannot be explained on the drawings • Statement of which person did what for every submission in both weeks • All submissions except the spreadsheets and VM presentation can be electronic via Learn or on paper; the choice is yours • Spreadsheets and presentation must be electronic files (Excel and Powerpoint)

  15. Marking Scheme • PFD and Letter • 5% • Plan Drawings of Options • 20% • VM Presentation & VM Report • 25% • Does not include marks for drawings already submitted • Process Calculations for Preferred Option • 15% • Final Design • 35% • For BEng, submissions are the same but quality expectations are less by a factor of 10/11 • Marks are awarded for technical feasibility, appropriateness of solutions, and clarity, detail and conciseness of communications • You will note that no long written report is needed… • This means the drawings need a lot of work…

  16. Feedback • Rapid brief feedback on PFD and letter to indicate whether appropriate standard is being achieved • Verbal feedback on options drawings if necessary (eg if one is obviously stupid) • Verbal feedback at VM meeting • Remaining aspects will be subject to written feedback after submission • This may take up to six weeks due to MWH involvement

  17. Staff • Dr Martin Crapper • Academic Responsible • Will “role play” client as necessary • Make it clear whom you are asking! • Room 3.18 William Rankine Building • Away on 17th,21st & 22nd January • MWH Engineers • Martin Pettinger • Ian Lang • Can be emailed if necessary

More Related