SlideServe
Menu
Préférences
© SlideServe · v2026

BT Hardware Commissioning

jude avatar
4 diapositives · 177 Views · Sep 13, 2014

This document outlines the hardware commissioning and testing schedule for various beam dumping and injection systems (MKI, MKQA, MKD, MKB) at specified LHC points. Installation timelines are detailed, with significant milestones spanning from summer 2005 to spring 2007. Procedures for hardware commissioning, system-level tests, and a reliability run of the beam dumping system are emphasized. Detailed planning is necessary to ensure cohesive hardware commissioning activities and mitigate interference risks. Compliance with EDMS documentation throughout the project is critical.

BT Hardware Commissioning - slide 1
01 / 4BT Hardware Commissioning
1 / 17

Télécharger la présentation

BT Hardware Commissioning
Une image / un lien ci-dessous est fourni (tel quel) pour télécharger la présentation

Politique de téléchargement : le contenu du site vous est fourni TEL QUEL pour votre information et votre usage personnel ; il ne peut être vendu, concédé sous licence ni partagé sur d’autres sites sans l’accord de son auteur.Le contenu vous est fourni TEL QUEL, pour votre information et votre usage personnel uniquement. Téléchargez la présentation en cliquant sur ce lien. Lors du téléchargement, si vous ne parvenez pas à télécharger une présentation, l’éditeur a peut-être supprimé le fichier de son serveur.Pendant le téléchargement, si vous ne parvenez pas à obtenir une présentation, le fichier a peut-être été supprimé par l’éditeur.

F I N

Plus de contenu associé

Transcription de la présentation
  1. BT Hardware Commissioning • BT Coordinated Systems System Tests • TI 8 part downstream of TED87765 + injection system in point 8Idem TI 2 / point 2 • LHC Beam Dumping System in point 6 • BT Equipment • Injection kickers MKI in point 2 and 8 • Tune/aperture kickers MKQA in point 4 • Beam dump kickers MKD and dilution kickers MKB in point 6 • Protection elements TCDS and TCDQ point 6 J.Uythoven, V.Mertens & B.Goddard HC review 13 Mai 2005

  2. Kickers MKI and MKQA • MKI point 8: • Installation: summer (generators, HV cables) autumn – winter (magnets) 2005 • Hardware Commissioning likely during spring / summer 2006 • Hardware Commissioning test procedures described in EDMS document 481639 • Need to be ready for Sector Test in November 2006 • MKI point 2 • Installation: t.b.defined • Hardware Commissioning in spring 2007 • Procedures defined & published, as for point 8 • MKQA point 4 • Installation: after MKI point 2 • Likely not synchronous with other HC activities in point 4 HC review 13 Mai 2005

  3. Beam Dumping System Point 6 • Kickers: • Installation extraction kickers MKD spring 2006 Installation dilution kickers MKB summer 2006 • Hardware Commissioning winter 2006 / 2007 • Procedures: EDMS document in preparation • Protection elements TCDS and TCDQ • Installation summer 2006 • Hardware Commissioning winter 2006 / 2007 • Procedures in same EDMS document as kickers, in preparation • Needs to be followed by reliability run of three months (of the complete beam dumping system !) • System level commissioning • In spring 2007 • In parallel with hardware commissioning in point 2 HC review 13 Mai 2005

  4. Main concerns • Detailed planning of equipment HC activities needed, especially to check for interferences (include in LHC planning!). • Detailed planning of system level tests (scheduling and responsibility) to be defined. • Critical path for TI 2 end and IR2 injection. • Beam dumping system reliability run to be included in LHC planning. HC review 13 Mai 2005